1325 N WETHERLY DR 90069

Certificate Information: 1325 N WETHERLY DR 90069

Application / Permit
22047-10000-00944
Plan Check / Job No.
B22LA08707
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SWIMMING POOL WITH SPA
Permit Issued
Issued on 4/20/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 CARLOS MONTES
Corrections Issued 6/1/2022 CARLOS MONTES
Quality Review Completed 6/3/2022 KEN GILL
Building Plans Picked Up 6/7/2022 APPLICANT
Applicant returned to address corrections 9/15/2022 CARLOS MONTES
Applicant returned to address corrections 9/29/2022 CARLOS MONTES
Applicant returned to address corrections 12/20/2022 CARLOS MONTES
Plan Check Approved 4/17/2023 CARLOS MONTES
Issued 4/20/2023 APPLICANT
CofO in Progress 7/9/2024 RAUL BARAJAS
CofO in Progress 7/11/2024 RAUL BARAJAS
CofO in Progress 7/11/2024 RAUL BARAJAS
Permit Finaled 7/16/2024 RONALD MYRICK
CofO Issued 7/16/2024 RONALD MYRICK
Permit Finaled 7/16/2024 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/17/2023 CARLOS MONTES

Contact Information

Contractor Peter Terpinski; Lic. No.: 956472-B 5212 1/2 FOUNTAIN AVENUE 3      LOS ANGELES, CA 90029

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 7/5/2023 Corrections Issued STUART CHAPMAN
Pre-Gunite 8/15/2023 Partial Approval RAUL BARAJAS
Enclosure/Fence 5/6/2024 Corrections Issued RAUL BARAJAS
Enclosure/Fence 5/9/2024 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/4/2024 Approved RAUL BARAJAS
Final 6/4/2024 Corrections Issued RAUL BARAJAS
Pre-Gunite 6/4/2024 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Not Ready RAUL BARAJAS
Final 6/18/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready RAUL BARAJAS
Final 6/25/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Approved RAUL BARAJAS
Final 7/9/2024 OK to Issue CofO RAUL BARAJAS