10433 W LINDBROOK DR 90024

Certificate Information: 10433 W LINDBROOK DR 90024

Application / Permit
22047-10000-00935
Plan Check / Job No.
B22LA08585
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan New 18' x 40' pool + spa with automatic cover per standard plan #268.
Permit Issued
Issued on 6/3/2022
Issuing Office
Current Status
CofO Issued on 11/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/13/2022 SAMUEL GONZALEZ
Corrections Issued 5/14/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 5/24/2022 SAMUEL GONZALEZ
Plan Check Approved 6/1/2022 SAMUEL GONZALEZ
Issued 6/3/2022 APPLICANT
CofO in Progress 11/19/2024 STEPHANIE SWANSON
Permit Finaled 11/25/2024 RICHARD STEINBACH
CofO Issued 11/25/2024 RICHARD STEINBACH
Permit Finaled 11/25/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/19/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/31/2022 Corrections Issued STEPHANIE SWANSON
Gas Piping or Gas Test 8/31/2022 Partial Approval STEPHANIE SWANSON
Pool Piping 8/31/2022 Approved STEPHANIE SWANSON
Pre-Gunite 8/31/2022 Conditional Approval STEPHANIE SWANSON
Rough-Electrical 8/31/2022 Approved STEPHANIE SWANSON
Rough-Plumbing 8/31/2022 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/2/2022 Approved STEPHANIE SWANSON
Grounding or Bonding 1/20/2023 Corrections Issued STEPHANIE SWANSON
Grounding or Bonding 2/3/2023 Corrections Issued STEPHANIE SWANSON
Deck 2/21/2023 Approved STEPHANIE SWANSON
Enclosure/Fence 7/31/2023 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 9/24/2024 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 10/2/2024 Approved STEPHANIE SWANSON
Equipment Noise Level 10/15/2024 Approved JUAN ESCOTO DELGADO
Pre-Gunite 10/16/2024 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved STEPHANIE SWANSON
Final 10/22/2024 Corrections Issued STEPHANIE SWANSON
Final 11/19/2024 OK to Issue CofO STEPHANIE SWANSON