- eplan: 15'X22.5' New Pool and 7.5'X7.5' SPA PER STANDARD POOL STRUCTURAL PLAN #268
- Permit Issued
- Issued on 12/14/2022
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | SUNMIN LEE |
| Corrections Issued | 5/2/2022 | SUNMIN LEE |
| Plan Check Approved | 12/1/2022 | SUNMIN LEE |
| Issued | 12/14/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | MISAEL ESPARZA |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
| CofO Issued | 5/29/2024 | RUBEN SALAS |
| Permit Finaled | 5/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction within easement | Cleared | 8/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | T & N Remodeling Inc; Lic. No.: 1063782-B | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Rough-Plumbing | 5/18/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Pool Piping | 5/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Rough-Plumbing | 5/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Corrections Issued | JOHN COLEMAN |
| Pool Piping | 5/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Rough-Plumbing | 5/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Pool Piping | 6/5/2023 | Partial Approval | THOMAS FINNILA |
| Pre-Gunite | 6/5/2023 | Approved | THOMAS FINNILA |
| Gas Piping or Gas Test | 9/8/2023 | Partial Approval | MISAEL ESPARZA |
| Enclosure/Fence | 11/15/2023 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 11/27/2023 | Corrections Issued | MISAEL ESPARZA |
| Grounding or Bonding | 11/27/2023 | Corrections Issued | MISAEL ESPARZA |
| Deck | 12/1/2023 | Approved | CHRISTOPHER ROJAS |
| Grounding or Bonding | 12/1/2023 | Approved | CHRISTOPHER ROJAS |
| Enclosure/Fence | 12/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Equipment Noise Level | 12/5/2023 | Not Ready for Inspection | FELIPE PENICHE |
| Pool Equipment Noise Test | 12/5/2023 | Not Ready for Inspection | FELIPE PENICHE |
| Enclosure/Fence | 12/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/15/2024 | Approved | MISAEL ESPARZA |
| Final | 3/15/2024 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | MISAEL ESPARZA |
| Pool Equipment Noise Test | 3/19/2024 | Approved | FELIPE PENICHE |
| Final | 4/12/2024 | Corrections Issued | JOHN COLEMAN |
| Final | 5/22/2024 | OK to Issue CofO | MISAEL ESPARZA |