9246 W SIERRA MAR DR 90069

Certificate Information: 9246 W SIERRA MAR DR 90069

Application / Permit
22047-10000-00814
Plan Check / Job No.
B22LA07280
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AT HILLSIDE AREA
Permit Issued
Issued on 10/31/2022
Issuing Office
Current Status
Issued on 10/31/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 YOUNG KIM
Corrections Issued 5/16/2022 YOUNG KIM
Quality Review Completed 6/3/2022 FARUK SEZER
Applicant returned to address corrections 8/5/2022 YOUNG KIM
Applicant returned to address corrections 9/20/2022 YOUNG KIM
Applicant returned to address corrections 10/25/2022 YOUNG KIM
Plan Check Approved 10/31/2022 YOUNG KIM
Issued 10/31/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/6/2022 YOUNG KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 7/13/2023 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/21/2023 Partial Approval RAUL BARAJAS
Grading Pre-Inspection 8/21/2023 No Access for Inspection STUART CHAPMAN
Piling/Pier/Caisson 8/21/2023 No Access for Inspection STUART CHAPMAN
Piling/Pier/Caisson 8/30/2023 Corrections Issued RAUL BARAJAS
Piling/Pier/Caisson 9/8/2023 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 9/11/2023 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/13/2023 Approved RAUL BARAJAS
Pre-Gunite 11/13/2023 Corrections Issued RAUL BARAJAS
Pool Piping 11/16/2023 Approved RAUL BARAJAS
Pre-Gunite 11/16/2023 Approved RAUL BARAJAS
Gas Piping or Gas Test 12/11/2023 Approved RICHARD DOCKUS
Pool Piping 12/11/2023 Approved RICHARD DOCKUS