4955 N MURIETTA AVE 91423

Certificate Information: 4955 N MURIETTA AVE 91423

Application / Permit
22047-10000-00748
Plan Check / Job No.
B22LA06692
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED SWIMMING POOL WITH SPA PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 6/20/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 JOSEPH RAFOLS
Corrections Issued 4/14/2022 JOSEPH RAFOLS
Building Plans Picked Up 12/6/2022 APPLICANT
Plan Check Approved 2/6/2023 LAWRENCE QUIRANTE
Issued 6/20/2024 APPLICANT
CofO in Progress 11/4/2024 MISAEL ESPARZA
Permit Finaled 11/15/2024 DANIEL ORRANTE
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 2/2/2023 RIDWAN HARDY

Contact Information

Architect Ro,, Jungdack; Lic. No.: C31119 4931 MURIETTA AVENUE      SHERMAN OAKS, CA 91423
Contractor R K S Zone Inc; Lic. No.: 961017-B 2333 BEVERLY BLVD #200      LOS ANGELES, CA 90057
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 8/27/2024 Partial Approval VINCENT HANLEY
Rough-Plumbing 8/27/2024 Corrections Issued VINCENT HANLEY
Rough-Plumbing 9/5/2024 Not Ready for Inspection MISAEL ESPARZA
Gunite 9/16/2024 Corrections Issued MISAEL ESPARZA
Enclosure/Fence 10/1/2024 Corrections Issued MISAEL ESPARZA
Enclosure/Fence 10/7/2024 Not Ready for Inspection MISAEL ESPARZA
Enclosure/Fence 10/16/2024 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/16/2024 Approved MISAEL ESPARZA
Final 10/16/2024 Corrections Issued MISAEL ESPARZA
Pre-Gunite 10/16/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved MISAEL ESPARZA
Final 10/22/2024 Corrections Issued MISAEL ESPARZA
Pre-Gunite 10/22/2024 Approved MISAEL ESPARZA
Equipment Noise Level 10/29/2024 Approved FELIPE PENICHE
Final 10/31/2024 OK to Issue CofO MISAEL ESPARZA