12250 W MORRISON ST 91607
Certificate Information: 12250 W MORRISON ST 91607
- Application / Permit
- 22047-10000-00640
- Plan Check / Job No.
- B22LA05481
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 18' x 25' Pool within 6' x 6' spa with water featureand std plan #270
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2022 | JOSEPH RAFOLS |
| Corrections Issued | 5/3/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 5/20/2022 | PINANK PATEL |
| Building Plans Picked Up | 6/23/2022 | APPLICANT |
| Plan Check Approved | 9/28/2022 | JOSEPH RAFOLS |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 3/6/2024 | MISAEL ESPARZA |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
| CofO Issued | 3/21/2024 | RUBEN SALAS |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/5/2022 | MAXFIELD VERMY |
| Construction near power lines | Cleared | 5/11/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Royal Moon Pools Inc; Lic. No.: 1041907-C53 | P O BOX 1044 ROSAMOND, CA 93560 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/17/2022 | Corrections Issued | CALEB MEISTER |
| Pre-Gunite | 12/5/2022 | Approved | KIRK SANDERS |
| Gas Piping or Gas Test | 8/14/2023 | Approved | KIRK SANDERS |
| Grounding or Bonding | 8/14/2023 | Approved | KIRK SANDERS |
| Deck | 12/7/2023 | Approved | KIRK SANDERS |
| Enclosure/Fence | 12/7/2023 | Corrections Issued | KIRK SANDERS |
| Grounding or Bonding | 12/7/2023 | Approved | KIRK SANDERS |
| Pool Equipment Noise Test | 2/13/2024 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Approved | JOSE AVILA |
| Final | 2/16/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | JOSE AVILA |
| Final | 2/26/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 3/1/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Pre-Inspection | 3/6/2024 | Approved | JUAN VALENZUELA |