11006 W CASHMERE ST 90049
Certificate Information: 11006 W CASHMERE ST 90049
- Application / Permit
- 22047-10000-00529
- Plan Check / Job No.
- B22LA04704
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New residential pool/spa per LA Standard plan #268
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Current Status
- CofO Issued on 10/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2022 | JAD BASMA |
| Corrections Issued | 3/29/2022 | JAD BASMA |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 6/2/2022 | JAD BASMA |
| Issued | 6/2/2022 | APPLICANT |
| CofO in Progress | 10/6/2023 | CARLOS MATAMOROS |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
| CofO Issued | 10/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/17/2022 | JAD BASMA |
Contact Information
| Contractor | Bookie Development Inc; Lic. No.: 977585-B | 10509 CLARKSON ROAD LOS ANGELES, CA 90064 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/30/2022 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 8/3/2022 | Approved | CARLOS MATAMOROS |
| Gunite | 8/3/2022 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 8/3/2022 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 8/3/2022 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 8/3/2022 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 8/23/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deck | 9/27/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 9/27/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 4/14/2023 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 8/11/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 8/11/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Equipment Noise Level | 8/24/2023 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Approved | CHRISTOPHER WILSON |
| Final | 8/30/2023 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Final | 9/13/2023 | Partial Approval | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 10/5/2023 | OK to Issue CofO | CARLOS MATAMOROS |