8917 S KITTYHAWK AVE 90045
Certificate Information: 8917 S KITTYHAWK AVE 90045
- Application / Permit
- 22047-10000-00489
- Plan Check / Job No.
- B22LA04388
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan Proposed swimming pool/spa. 30 x15 poos and 7x7 spa per STD plan# 268.
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/17/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/29/2022 | MICHAEL LOPEZ |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 3/21/2025 | JESUS PINEDA |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
| CofO Issued | 3/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pool Icons Inc; Lic. No.: 479446-C53 | 15935 DEL PRADO DR HACIENDA HEIGHTS, CA 91745 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Approved | BOBBY KEY |
| Grounding or Bonding | 5/23/2022 | Approved | BOBBY KEY |
| Pool Piping | 5/23/2022 | Approved | BOBBY KEY |
| Pre-Gunite | 5/23/2022 | Approved | BOBBY KEY |
| Deck | 7/7/2022 | Approved | BOBBY KEY |
| Enclosure/Fence | 8/5/2022 | Corrections Issued | BOBBY KEY |
| Enclosure/Fence | 8/8/2022 | Approved | BOBBY KEY |
| Final | 8/18/2022 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Not Ready | HERBERT GIRON |
| Final | 9/7/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Not Ready | BOBBY KEY |
| Pool Equipment Noise Test | 9/29/2022 | Approved | JAMES VORHIS |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Not Ready | BOBBY KEY |
| Final | 10/21/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Not Ready | BOBBY KEY |
| Final | 1/13/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/26/2024 | Corrections Issued | BOBBY KEY |
| Final | 7/26/2024 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/21/2025 | Approved | JESUS PINEDA |
| Final | 3/21/2025 | OK to Issue CofO | JESUS PINEDA |