3530 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3530 S MOUNTAIN VIEW AVE 90066

Application / Permit
22047-10000-00474
Plan Check / Job No.
B22LA04166
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 5/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 MAHNAZ NOURHASHEMI
Corrections Issued 3/25/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 3/30/2022 KEN GILL
Building Plans Picked Up 4/27/2022 APPLICANT
Applicant returned to address corrections 5/25/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 6/28/2022 MAHNAZ NOURHASHEMI
Issued 7/14/2022 APPLICANT
Permit Finaled 5/9/2025 RICHARD STEINBACH
Permit Finaled 5/9/2025 RICHARD STEINBACH
CofO Issued 5/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 5/14/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 5/16/2022 SAUL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/2/2024 Approved JESUS PINEDA
Pool Piping 5/2/2024 Partial Approval JESUS PINEDA
Pre-Gunite 5/2/2024 Approved JESUS PINEDA
Rough-Plumbing 5/2/2024 Partial Approval JESUS PINEDA
Gas Piping or Gas Test 10/11/2024 Approved DANIEL VERA
Rough-Electrical 10/11/2024 Approved DANIEL VERA
Deck 11/26/2024 Approved DANIEL VERA
Grounding or Bonding 11/26/2024 Approved DANIEL VERA
Enclosure/Fence 3/21/2025 Approved WILBER ROSALES
Special/Order Compliance 3/21/2025 Partial Inspection TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready WILBER ROSALES
Final 4/30/2025 Conditional Approval WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved WILBER ROSALES