2405 S HAUSER BLVD 90016
Certificate Information: 2405 S HAUSER BLVD 90016
- Application / Permit
- 22047-10000-00443
- Plan Check / Job No.
- B22LA03918
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW 8'X18'SPA FOR 30 UNIT APARTMENT BUILDING (see comments)
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 9/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | MINA HABIB |
| Corrections Issued | 4/11/2022 | MINA HABIB |
| Quality Review Completed | 4/12/2022 | FARUK SEZER |
| Disabled Access Plans Picked Up | 4/12/2022 | APPLICANT |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| Applicant returned to address corrections | 7/7/2022 | MINA HABIB |
| Applicant returned to address corrections | 7/29/2022 | MINA HABIB |
| Plan Check Approved | 10/17/2022 | MINA HABIB |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 9/27/2023 | ALFREDO LOPEZ |
| CofO in Progress | 7/2/2024 | EDWIN GREGORYONA |
Permit Application Clearance Information
| Public Swimming Pool approval | Cleared | 10/3/2022 | LACDHS APPROVED |
| DAS Clearance | Cleared | 10/5/2022 | SHINE LIN |
Contact Information
| Contractor | California Pool Service; Lic. No.: 945871-D35 | P O BOX 604 ARTESIA, CA 90702 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/20/2023 | Conditional Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 1/30/2023 | Partial Approval | ALFREDO LOPEZ |
| Pre-Gunite | 1/30/2023 | Partial Inspection | ALFREDO LOPEZ |
| Deputy Shotcrete | 2/3/2023 | Approved | ALFREDO LOPEZ |
| Grounding or Bonding | 2/16/2023 | Partial Approval | ALFREDO LOPEZ |
| Enclosure/Fence | 4/19/2023 | Partial Approval | ALFREDO LOPEZ |
| Enclosure/Fence | 4/24/2023 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | ALFREDO LOPEZ |
| Grounding or Bonding | 4/24/2023 | Approved | ALFREDO LOPEZ |
| Pre-Gunite | 4/24/2023 | Approved | ALFREDO LOPEZ |
| Pre-Inspection | 4/24/2023 | Approved | ALFREDO LOPEZ |
| Enclosure/Fence | 6/15/2023 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Approved | ALFREDO LOPEZ |
| Grounding or Bonding | 6/15/2023 | Approved | ALFREDO LOPEZ |
| Pre-Gunite | 6/15/2023 | Approved | ALFREDO LOPEZ |
| Final | 8/16/2023 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | ALFREDO LOPEZ |
| Final | 8/29/2023 | Conditional Approval | ALFREDO LOPEZ |