20851 W MARTHA ST 91367

Certificate Information: 20851 W MARTHA ST 91367

Application / Permit
22047-10000-00368
Plan Check / Job No.
B22LA03199
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW POOL & SPA
Permit Issued
Issued on 7/25/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/7/2022 ZAW HAN
Corrections Issued 3/10/2022 ZAW HAN
Building Plans Picked Up 3/11/2022 APPLICANT
Plan Check Approved 7/12/2022 MINA HABILI
Issued 7/25/2022 APPLICANT
CofO in Progress 6/23/2023 ALEXANDER HANDY
Permit Finaled 11/21/2025 MICHAEL PELHAM
CofO Issued 11/21/2025 MICHAEL PELHAM
Permit Finaled 11/21/2025 MICHAEL PELHAM

Permit Application Clearance Information

Construction near power lines Cleared 7/6/2022 TINA MIRANDA
Grading Pre-Inspection Cleared 7/12/2022 ZAW HAN

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2022 Corrections Issued STEVEN BACK
Gas Piping or Gas Test 9/27/2022 Corrections Issued STEVEN BACK
Pool Piping 9/27/2022 Not Ready for Inspection STEVEN BACK
Pre-Gunite 9/27/2022 Corrections Issued STEVEN BACK
Rough-Electrical 9/27/2022 Not Ready for Inspection STEVEN BACK
Rough-Plumbing 9/27/2022 Not Ready for Inspection STEVEN BACK
Pool Piping 9/29/2022 Corrections Issued STEVEN BACK
Pre-Gunite 11/10/2022 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 11/21/2022 Approved STEVEN BACK
Grounding or Bonding 11/21/2022 Partial Approval STEVEN BACK
Pre-Gunite 11/21/2022 Approved STEVEN BACK
Rough-Plumbing 11/21/2022 Approved STEVEN BACK
Deck 3/3/2023 Approved ALEXANDER HANDY
Enclosure/Fence 3/13/2023 Corrections Issued JON MCHUGH
Enclosure/Fence 3/17/2023 Approved ALEXANDER HANDY
Final 5/10/2023 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Not Ready ALEXANDER HANDY
Final 6/22/2023 OK to Issue CofO ALEXANDER HANDY
Rough-Electrical 6/22/2023 Approved ALEXANDER HANDY
Rough-Plumbing 6/22/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Approved ALEXANDER HANDY
Pool Equipment Noise Test 6/30/2023 Approved ALFREDO FLORES