13458 W CUMPSTON ST 91401
Certificate Information: 13458 W CUMPSTON ST 91401
- Application / Permit
- 22047-10000-00343
- Plan Check / Job No.
- B22LA03047
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- *EPLAN* NEW POOL (17' X 32') ANDC SPA (6' X 6') PER STD PLAN 268. JR Pool and Spa Services Lic. # C-53 771197 Bis Lic. # 2739667
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- CofO Issued on 12/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2022 | VIVIAN LAO |
| Corrections Issued | 2/24/2022 | VIVIAN LAO |
| Plan Check Approved | 3/1/2022 | VIVIAN LAO |
| Issued | 3/4/2022 | APPLICANT |
| CofO in Progress | 12/24/2024 | RYAN SALAZAR |
| Permit Finaled | 12/30/2024 | RUBEN SALAS |
| CofO Issued | 12/30/2024 | RUBEN SALAS |
| Permit Finaled | 12/30/2024 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Jr Pool & Spa Services; Lic. No.: 771197-C53 | P O BOX 5249 NORTH HOLLYWOOD, CA 91616 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/9/2022 | Corrections Issued | RICHARD DOCKUS |
| Grounding or Bonding | 3/14/2022 | Approved | MICHEL ABAJAN |
| Pool Piping | 3/14/2022 | Approved | MICHEL ABAJAN |
| Pre-Gunite | 3/14/2022 | Approved | MICHEL ABAJAN |
| Deputy Grading | 3/15/2022 | Conditional Approval | ALAN MORELOS |
| Deputy Shotcrete | 3/16/2022 | Conditional Approval | MICHAEL TEMPLE |
| Gas Piping or Gas Test | 4/19/2023 | Approved | JOHN COLEMAN |
| Deck | 8/15/2023 | Approved | RYAN SALAZAR |
| Enclosure/Fence | 8/15/2023 | Approved | RYAN SALAZAR |
| Equipment Noise Level | 10/11/2023 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Approved | RYAN SALAZAR |
| Final | 10/11/2023 | Partial Approval | RYAN SALAZAR |
| Pool Equipment Noise Test | 10/11/2023 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Approved | RYAN SALAZAR |
| Final | 12/20/2024 | OK to Issue CofO | RYAN SALAZAR |