20524 W LASSEN ST 91311
Certificate Information: 20524 W LASSEN ST 91311
- Application / Permit
- 22047-10000-00165
- Plan Check / Job No.
- B22LA01417
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Commercial
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW HOTEL PUBLIC SWIMMING POOL 15' X 40'.
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 2/24/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 3/2/2022 | PETER KIM |
| Disabled Access Plans Picked Up | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Applicant returned to address corrections | 12/27/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 1/6/2023 | ARMEN JIVALAGIAN |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 3/19/2024 | JEFFREY DURAN |
| Permit Finaled | 3/19/2024 | JEFFREY DURAN |
| CofO Issued | 3/19/2024 | JEFFREY DURAN |
| Permit Finaled | 3/19/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2022 | CARLOS AGUILERA |
| "D" conditions | Cleared | 8/30/2022 | DALIA MOKAYED |
| "Q" conditions | Cleared | 8/30/2022 | DALIA MOKAYED |
| Miscellaneous | Cleared | 8/30/2022 | DALIA MOKAYED |
| Tract Map conditions | Cleared | 8/30/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 8/30/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 8/30/2022 | DALIA MOKAYED |
| Excavation more than 5-ft deep | Cleared | 9/6/2022 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 9/26/2022 | ARMEN JIVALAGIAN |
| CPC | Cleared | 9/27/2022 | DALIA MOKAYED |
| Sewer availability | Cleared | 10/7/2022 | ABDULLAH SADOZAI |
| Public Swimming Pool approval | Cleared | 12/27/2022 | LACDHS APPROVED |
Contact Information
| Contractor | Bodar Enterprises; Lic. No.: 536360-B | P O BOX 892110 TEMECULA, CA 92589 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Pelayo,, Jorge A; Lic. No.: C91269 | 1102 VINTAGE CIRCLE CORONA, CA 92881 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Grounding or Bonding | 1/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Pre-Gunite | 1/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Rough-Electrical | 1/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Rough-Plumbing | 1/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Pre-Gunite | 3/20/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2023 | Approved | JEFFREY FULTON |
| Grounding or Bonding | 3/24/2023 | Approved | JEFFREY FULTON |
| Pre-Gunite | 3/24/2023 | Approved | JEFFREY FULTON |
| Deputy Shotcrete | 3/28/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Deck | 4/12/2023 | Partial Inspection | JEFFREY FULTON |
| Grounding or Bonding | 4/12/2023 | Not Ready for Inspection | JEFFREY FULTON |
| ELECTRICAL-Final | 10/10/2023 | Approved | JEFFREY FULTON |
| Final | 10/10/2023 | Conditional Approval | JEFFREY FULTON |
| PLUMBING-Final | 10/10/2023 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | JEFFREY FULTON |
| Special/Order Compliance | 10/10/2023 | Approved | JEFFREY FULTON |
| Final | 10/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 3/19/2024 | OK to Issue CofO | JEFFREY DURAN |