401 E CARROLL CL 90291

Certificate Information: 401 E CARROLL CL 90291

Application / Permit
22047-10000-00133
Plan Check / Job No.
B21LA13922
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan : INSTALL NEW( 5'-5" X 8'-0") PREFAB SPA AT (E) ROOF OF (E) 2 STYORY SINGLE FAMILY DWELLING (building permit under permit # 21016-10000-19324). COMPLY WITH DEPARTMENT ORDER effective date 06/09/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO in Progress on 11/29/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/22/2021 GARO TELMI
Corrections Issued 8/24/2021 GARO TELMI
Quality Review Completed 9/2/2021 MICHAEL PEREZ
Plan Check Approved 1/24/2022 GARO TELMI
No Progress 1/24/2022 GARO TELMI
Plan Check Approved 1/24/2022 GARO TELMI
Issued 4/20/2022 APPLICANT
CofO in Progress 11/29/2023 JOHN MATTILLO

Permit Application Clearance Information

No Data Available.

Contact Information

Architect , ; Lic. No.: C35166 16800 DEVONSHIRE ST   307    GRANADA HILLS, CA 91344
Contractor Insteel Llc; Lic. No.: 990797-C53 2101 ENTERPRISE DR NE      LELAND, NC 28451
Engineer Padilla,, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2022 No Access for Inspection MARIAN PODPORA
Final 9/16/2022 No Access for Inspection MARIAN PODPORA
Pre-Gunite 9/16/2022 No Access for Inspection MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Not Ready MARIAN PODPORA
Excavation/Setback/Form/Re-Bar 9/19/2022 Approved MARIAN PODPORA
Final 9/19/2022 Corrections Issued MARIAN PODPORA
Pre-Gunite 9/19/2022 Approved MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved MARIAN PODPORA
Final 10/31/2022 No Access for Inspection RYAN BARNES
Final 11/3/2022 Corrections Issued MARIAN PODPORA
Final 11/22/2022 Corrections Issued MARIAN PODPORA
Final 11/29/2023 Conditional Approval JOHN MATTILLO