4009 W 58TH PL 90043

Certificate Information: 4009 W 58TH PL 90043

Application / Permit
22047-10000-00125
Plan Check / Job No.
B22LA01133
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN
Permit Issued
Issued on 4/14/2022
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2022 KHUONG TRUONG
Corrections Issued 1/26/2022 KHUONG TRUONG
Applicant returned to address corrections 3/3/2022 SAMUEL GONZALEZ
Plan Check Approved 4/5/2022 GEORGE ALVAREZ
Issued 4/14/2022 APPLICANT
Building Plans Picked Up 4/15/2022 APPLICANT
CofO in Progress 6/29/2023 ENRIQUE MIRELES
CofO in Progress 6/29/2023 ENRIQUE MIRELES
Permit Finaled 7/8/2023 DEROLD HAUFF
CofO Issued 7/8/2023 DEROLD HAUFF
Permit Finaled 7/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 2/23/2022 RIDWAN HARDY

Contact Information

Contractor Blue Fountain Pools And Spas Inc; Lic. No.: 1004554-C53 1151 S GRAND AVE      GLENDORA, CA 91740
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/24/2023 Approved ENRIQUE MIRELES
Pre-Gunite 3/24/2023 Approved ENRIQUE MIRELES
Rough-Electrical 4/14/2023 Not Ready for Inspection ENRIQUE MIRELES
Deputy Shotcrete 4/17/2023 Approved ENRIQUE MIRELES
Rough-Electrical 4/19/2023 Approved ENRIQUE MIRELES
Deck 5/15/2023 Approved ENRIQUE MIRELES
Enclosure/Fence 5/22/2023 Corrections Issued ENRIQUE MIRELES
Enclosure/Fence 5/26/2023 Approved ENRIQUE MIRELES
Pool Equipment Noise Test 6/14/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/15/2023 Approved ENRIQUE MIRELES
Final 6/15/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved ENRIQUE MIRELES
Final 6/28/2023 OK to Issue CofO ENRIQUE MIRELES