1417 N FERMO DR 90272
Certificate Information: 1417 N FERMO DR 90272
- Application / Permit
- 22047-10000-00121
- Plan Check / Job No.
- B22LA01066
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL AND SPA
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 2/7/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/17/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| Plan Check Approved | 4/18/2022 | MAHNAZ NOURHASHEMI |
| Issued | 4/18/2022 | APPLICANT |
| CofO in Progress | 3/3/2025 | KEVIN SARGSYAN |
| Permit Finaled | 3/12/2025 | RICHARD STEINBACH |
| CofO Issued | 3/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 4/5/2022 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 4/12/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Ceci Clarke Inc; Lic. No.: 1040135-B | 444 ARNEILL ROAD CAMARILLO, CA 93010 |
| Engineer | Vasquez,, Mario Alberto; Lic. No.: C89006 | 43023 40TH ST WEST LANCASTER, CA 93536 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 1/6/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Partial Approval | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 8/17/2023 | Approved | KEVIN SARGSYAN |
| Pre-Gunite | 8/17/2023 | Conditional Approval | KEVIN SARGSYAN |
| Pool Piping | 9/7/2023 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 11/20/2023 | Approved | KEVIN SARGSYAN |
| Deck | 5/31/2024 | Approved | EVAN COOPER |
| Enclosure/Fence | 9/12/2024 | Approved | EVAN COOPER |
| Pool Equipment Noise Test | 10/8/2024 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 11/19/2024 | Approved | KEVIN SARGSYAN |
| Final | 11/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 11/19/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 3/3/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | KEVIN SARGSYAN |