4189 S CLOVERDALE AVE 90008
Certificate Information: 4189 S CLOVERDALE AVE 90008
- Application / Permit
- 22047-10000-00048
- Plan Check / Job No.
- B22LA00390
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- SWIMMING POOL & SPA (#268) WITH ENGINEER DESIGN
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 6/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2022 | GEORGE ALVAREZ |
| Corrections Issued | 1/18/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 2/23/2022 | STANLEY RAAP |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Plan Check Approved | 3/15/2022 | FERNANDO FLORES |
| Issued | 3/18/2022 | APPLICANT |
| Refund in Progress | 4/19/2022 | TERENCE SHIA |
| Refund Withdrawn | 4/20/2022 | EMILY HU |
| Issued | 4/20/2022 | EMILY HU |
| CofO in Progress | 6/2/2023 | CHARLES BOGHOSKHAN |
| Permit Finaled | 6/3/2023 | DEROLD HAUFF |
| CofO Issued | 6/3/2023 | DEROLD HAUFF |
| Permit Finaled | 6/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/27/2022 | PATRICK MISCHLICH |
Contact Information
| Contractor | Pool Icons Inc; Lic. No.: 479446-C53 | 15935 DEL PRADO DR HACIENDA HEIGHTS, CA 91745 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 4/15/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Pre-Gunite | 4/15/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | Corrections Issued | ANTHONY EGSON |
| Pre-Gunite | 4/19/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Partial Inspection | ANTHONY EGSON |
| Deck | 7/15/2022 | Corrections Issued | ANTHONY EGSON |
| Grounding or Bonding | 7/15/2022 | Approved | ANTHONY EGSON |
| Grounding or Bonding | 8/4/2022 | Approved | ANTHONY EGSON |
| Enclosure/Fence | 10/4/2022 | Corrections Issued | ANTHONY EGSON |
| Enclosure/Fence | 10/11/2022 | No Access for Inspection | ANTHONY EGSON |
| Enclosure/Fence | 10/14/2022 | Approved | ANTHONY EGSON |
| Pool Equipment Noise Test | 2/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Approved | ANTHONY EGSON |
| Final | 4/11/2023 | Corrections Issued | ANTHONY EGSON |
| Pre-Gunite | 4/11/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 4/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/1/2023 | Approved | ANTHONY EGSON |
| Final | 6/1/2023 | OK to Issue CofO | ANTHONY EGSON |
| PLUMBING-Final | 6/1/2023 | Approved | ANTHONY EGSON |