438 N LA JOLLA AVE 90048
Certificate Information: 438 N LA JOLLA AVE 90048
- Application / Permit
- 22047-10000-00019
- Plan Check / Job No.
- B22LA00151
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- *EPLAN* (N) POOL (28'-1" X 14') AND SPA (8' X 7'-8") PER STD PLAN # 268. License # - 1046115 Class - C53 Tax ID - 3086745
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 9/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2022 | VIVIAN LAO |
| Corrections Issued | 1/6/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 1/28/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/8/2022 | VIVIAN LAO |
| Plan Check Approved | 2/27/2022 | KEVIN MORALES |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 9/3/2024 | BRENDAN MORELLI |
| Permit Finaled | 9/7/2024 | RUBEN SALAS |
| CofO Issued | 9/7/2024 | RUBEN SALAS |
| Permit Finaled | 9/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction within easement | Cleared | 2/22/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 7361 ETHEL AVE SUITE 4 NORTH HOLLYWOOD, CA 91605 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gunite | 3/22/2022 | No Access for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 3/24/2022 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 3/24/2022 | Approved | JOSEPH MCGARRY |
| Pool Piping | 3/24/2022 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 3/24/2022 | Approved | JOSEPH MCGARRY |
| Deputy Shotcrete | 4/1/2022 | Conditional Approval | ADAM ESCOTO |
| Grounding or Bonding | 8/14/2023 | Partial Approval | BRENDAN MORELLI |
| Grounding or Bonding | 10/20/2023 | Approved | LILIANA PORTILLO |
| Enclosure/Fence | 7/22/2024 | Corrections Issued | AMIR NAZARIAN |
| Enclosure/Fence | 8/1/2024 | Approved | AMIR NAZARIAN |
| Equipment Noise Level | 8/20/2024 | Approved | ANDEY CHAPARRO |
| Pool Equipment Noise Test | 8/20/2024 | Approved | ANDEY CHAPARRO |
| Final | 8/22/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | AMIR NAZARIAN |
| Final | 8/29/2024 | OK to Issue CofO | BRENDAN MORELLI |
| Special/Order Compliance | 8/29/2024 | Partial Approval | NICHOLAS LOPEZ |