4640 N COLUMBUS AVE 91403
Certificate Information: 4640 N COLUMBUS AVE 91403
- Application / Permit
- 22047-10000-00018
- Plan Check / Job No.
- B21LA24473
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- *EPLAN* NEW POOL (17' X 26') AND SPA (8' X 8') PER STD PLAN # 268.
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2022 | VIVIAN LAO |
| Corrections Issued | 1/19/2022 | VIVIAN LAO |
| Plan Check Approved | 1/24/2022 | VIVIAN LAO |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 2/13/2023 | THOMAS FINNILA |
| CofO in Progress | 2/13/2023 | THOMAS FINNILA |
| CofO in Progress | 2/24/2023 | THOMAS FINNILA |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/13/2022 | Corrections Issued | JACK KARGODORIAN |
| Pre-Gunite | 6/27/2022 | Approved | JACK KARGODORIAN |
| Deputy Shotcrete | 7/1/2022 | Partial Approval | JACK KARGODORIAN |
| Deck | 11/10/2022 | Corrections Issued | THOMAS FINNILA |
| Deck | 11/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Enclosure/Fence | 11/30/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Enclosure/Fence | 12/7/2022 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 12/19/2022 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Equipment Noise Level | 12/21/2022 | Approved | FELIPE PENICHE |
| Enclosure/Fence | 12/27/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 12/27/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 1/3/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Final | 1/6/2023 | Conditional Approval | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | JOHN COLEMAN |
| Final | 1/19/2023 | Corrections Issued | THOMAS FINNILA |
| Final | 1/24/2023 | Corrections Issued | THOMAS FINNILA |
| Final | 2/7/2023 | Corrections Issued | THOMAS FINNILA |
| Final | 2/13/2023 | OK to Issue CofO | THOMAS FINNILA |
| Final | 2/14/2023 | Corrections Issued | THOMAS FINNILA |