8304 S PERSHING DR 90293
Certificate Information: 8304 S PERSHING DR 90293
- Application / Permit
- 22030-30000-08719
- Plan Check / Job No.
- B22WL04349
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Gradgin for New retaining wall and ADU conversion
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 1/23/2024
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2022 | RICHARD GARCIA |
| Corrections Issued | 12/7/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 12/8/2022 | APPLICANT |
| Plan Check Approved | 12/21/2022 | EDWIN ESPIN |
| Issued | 6/6/2023 | APPLICANT |
| Permit Finaled | 1/22/2024 | VASIL MIHALEV |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Yakov Design & Build; Lic. No.: 1067993-B | 8055 W MANCHESTER AVE 510 PLAYA DEL REY, CA 90293 |
| Engineer | Hu,, Yang Ming; Lic. No.: C81754 | 13675 HILL GROVE ST CORONA, CA 92880 |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 6/20/2023 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 6/20/2023 | Partial Approval | AL GAMBLE |
| Initial Grading | 6/20/2023 | Approved | AL GAMBLE |
| Excavation | 8/4/2023 | Partial Approval | AL GAMBLE |
| Sub-Drain | 8/4/2023 | Partial Approval | AL GAMBLE |
| Sub-Drain | 8/5/2023 | Approved | VASIL MIHALEV |
| Bottom/Toe | 8/15/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation | 8/15/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Sub-Drain | 8/15/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 8/30/2023 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 8/30/2023 | Corrections Issued | AL GAMBLE |
| Sub-Drain | 8/30/2023 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 9/7/2023 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 9/7/2023 | Not Ready for Inspection | AL GAMBLE |
| Sub-Drain | 9/7/2023 | Partial Inspection | AL GAMBLE |
| Sub-Drain | 9/12/2023 | Corrections Issued | AL GAMBLE |
| Special/Order Compliance | 9/13/2023 | Not Ready for Inspection | VASIL MIHALEV |
| Bottom/Toe | 9/18/2023 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation | 9/18/2023 | Approved | VASIL MIHALEV |
| Sub-Drain | 9/18/2023 | Not Ready for Inspection | VASIL MIHALEV |
| Sub-Drain | 10/5/2023 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 1/16/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 1/16/2024 | Not Ready for Inspection | AL GAMBLE |
| Rough | 1/16/2024 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 1/22/2024 | Approved | VASIL MIHALEV |
| Final | 1/22/2024 | Permit Finaled | VASIL MIHALEV |
| Rough | 1/22/2024 | Approved | VASIL MIHALEV |