11931-11933 W MODJESKA PL 90066

Certificate Information: 11931-11933 W MODJESKA PL 90066

Application / Permit
22030-30000-08210
Plan Check / Job No.
B22WL04388
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
R&R, SITE PREP FOR SINGLE FAMILY DWELLING UNDER 22010-30000-05841 AND GRADING FOR RETAINING WALL UNDER 23020-20000-00913 ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/15/2024
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 7/8/2026

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/13/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/14/2022 OMID HEDAYAT
Building Plans Picked Up 5/23/2023 APPLICANT
Applicant returned to address corrections 7/7/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/31/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 9/15/2023 SEWADA ZADOORAN MILAGARDI
Issued 8/15/2024 APPLICANT
Permit Finaled 7/8/2026 JOHNNY MIRANDA

Permit Application Clearance Information

Low Impact Development Cleared 6/6/2023 ROGELIO CORTES
Grading Pre-Inspection Cleared 9/1/2023 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Leshtz,, Harper Halprin; Lic. No.: C34496       ,
Contractor M X A Development Inc; Lic. No.: 1023633-B 1359 VIENNA WAY      VENICE, CA 90291
Engineer Djoneva,, Diana Ivanova; Lic. No.: C73805 3241 HENRIETTA AVE      LA CRESCENTA, CA 91214
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/19/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 8/30/2024 Corrections Issued MATTHEW JENKINS
Excavation 9/3/2024 Partial Inspection MATTHEW JENKINS
Special/Order Compliance 9/4/2024 Not Ready for Inspection VASIL MIHALEV
Bottom/Toe 9/9/2024 Partial Inspection MATTHEW JENKINS
Excavation 9/9/2024 Partial Approval MATTHEW JENKINS
Deputy Grading 9/24/2024 Conditional Approval MATTHEW JENKINS
Excavation 10/1/2024 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 12/10/2024 Approved MATTHEW JENKINS
Bottom/Toe 3/25/2025 Partial Approval JOHNNY MIRANDA
Excavation 3/25/2025 Partial Approval JOHNNY MIRANDA
Excavation 4/2/2025 Partial Approval JOHNNY MIRANDA
Initial Grading 4/2/2025 Partial Approval JOHNNY MIRANDA
Excavation 4/11/2025 Partial Inspection AL GAMBLE
Bottom/Toe 4/15/2025 Partial Approval MATTHEW JENKINS
Fill/Backfill 5/2/2025 Partial Approval AL GAMBLE
Sub-Drain 6/11/2025 Partial Inspection AL GAMBLE
Approved Compaction Report 6/24/2025 Approved JOHNNY MIRANDA
Drainage Devices/Catch Basin 11/18/2025 Partial Inspection AL GAMBLE
Final 6/8/2026 Not Ready for Inspection JESUS RODRIGUEZ
Bottom/Toe 6/17/2026 Approved JOHNNY MIRANDA
Final 6/17/2026 Corrections Issued JOHNNY MIRANDA
Rough 6/17/2026 Approved JOHNNY MIRANDA
Approved Compaction Report 7/2/2026 Approved JESUS RODRIGUEZ
Final 7/8/2026 Permit Finaled JOHNNY MIRANDA