247 N KENTER AVE 90049

Certificate Information: 247 N KENTER AVE 90049

Application / Permit
22030-30000-07831
Plan Check / Job No.
B22WL04227
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
R & R and infill existing pool, 1023 cy
Permit Issued
Issued on 6/13/2024
Issuing Office
Valley
Current Status
Issued on 6/13/2024

Permit Application Status History

Submitted 11/15/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 KAVIAN REFAHI
Corrections Issued 11/21/2022 KAVIAN REFAHI
Quality Review Completed 11/29/2022 CHIHARU SUZUKI
Building Plans Picked Up 11/29/2022 APPLICANT
Plan Check Approved 1/10/2023 KAVIAN REFAHI
Issued 6/13/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/10/2023 KAVIAN REFAHI
Hold Cleared 8/14/2024 TERESA RIVAS

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/15/2024 Partial Inspection JOHNNY MIRANDA
Approved Compaction Report 8/20/2024 Not Ready for Inspection AL GAMBLE
Deputy Grading 8/20/2024 Conditional Approval MATTHEW JENKINS
FLOOD-Proofing Certificate 8/20/2024 Not Ready for Inspection AL GAMBLE
Fill/Backfill 8/20/2024 Partial Inspection AL GAMBLE
Initial Grading 8/20/2024 Not Ready for Inspection AL GAMBLE
Rough 8/20/2024 Not Ready for Inspection AL GAMBLE
Deputy Grading 8/21/2024 Conditional Approval JOHNNY MIRANDA
Bottom/Toe 8/22/2024 Partial Approval JOHNNY MIRANDA
Excavation 8/22/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 8/26/2024 Partial Approval JOHNNY MIRANDA
Excavation 8/26/2024 Partial Approval JOHNNY MIRANDA
FLOOD-Proofing Certificate 8/26/2024 Partial Approval JOHNNY MIRANDA
Fill/Backfill 8/26/2024 Partial Approval JOHNNY MIRANDA
Rough 8/26/2024 Partial Approval JOHNNY MIRANDA
Excavation 8/28/2024 Partial Approval MATTHEW JENKINS
Fill/Backfill 8/28/2024 Partial Inspection MATTHEW JENKINS
Initial Grading 8/28/2024 Partial Inspection MATTHEW JENKINS
Deputy Grading 8/30/2024 Conditional Approval MATTHEW JENKINS
Excavation 9/5/2024 Approved VASIL MIHALEV
FLOOD-Proofing Certificate 9/5/2024 Not Ready for Inspection VASIL MIHALEV
Fill/Backfill 9/5/2024 Approved VASIL MIHALEV
Initial Grading 9/5/2024 Approved VASIL MIHALEV
Rough 9/5/2024 Not Ready for Inspection VASIL MIHALEV
Bottom/Toe 9/11/2024 Partial Approval JOHNNY MIRANDA
Excavation 9/11/2024 Partial Approval JOHNNY MIRANDA
FLOOD-Proofing Certificate 9/11/2024 Approved JOHNNY MIRANDA
Fill/Backfill 9/11/2024 Partial Approval JOHNNY MIRANDA
Initial Grading 9/11/2024 Partial Approval JOHNNY MIRANDA
Rough 9/11/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 9/18/2024 Partial Inspection JOHNNY MIRANDA
Excavation 9/18/2024 Partial Inspection JOHNNY MIRANDA
Fill/Backfill 9/18/2024 Partial Inspection JOHNNY MIRANDA
Initial Grading 9/18/2024 Partial Inspection JOHNNY MIRANDA
Rough 9/18/2024 Partial Inspection JOHNNY MIRANDA
Approved Compaction Report 9/20/2024 Approved VASIL MIHALEV
Special/Order Compliance 9/24/2024 Partial Inspection RUSSELL BONVOULOIR
Excavation 10/9/2024 Corrections Issued JOHNNY MIRANDA