2501 N BANYAN DR 90049
Certificate Information: 2501 N BANYAN DR 90049
- Application / Permit
- 22030-30000-04219
- Plan Check / Job No.
- B22WL02359
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Site grading for removing existing pool and new pool and deck
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/20/2026
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | KAVIAN REFAHI |
| Corrections Issued | 6/18/2022 | KAVIAN REFAHI |
| Quality Review Completed | 6/19/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/2/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/7/2022 | APPLICANT |
| Plan Check Approved | 9/23/2022 | KAVIAN REFAHI |
| Issued | 12/29/2023 | APPLICANT |
| Permit Finaled | 2/19/2026 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | ANTHONY MAINEZ |
| Watercourse | Cleared | 8/3/2022 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 9/2/2022 | KAVIAN REFAHI |
Contact Information
| Architect | Mahmoodi,, Arshia; Lic. No.: C34875 | 9832 YOAKUM DR BEVERLY HILLS, CA 90210 |
| Contractor | Coastal Design And Build Inc; Lic. No.: 1008762-C53 | 9560 TOPANGA CANYON BLVD UNIT 202 CHATSWORTH, CA 91311 |
| Engineer | Haro,, Ruben; Lic. No.: C72213 | 355 N LANTANA ST STE 492 CAMARILLO, CA 93010 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Geologist | Bovenizer,, Ernest; Lic. No.: EG2515 | 7622 GODDARD AVENUE LOS ANGELES, CA 90045 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/18/2024 | Partial Approval | JOHNNY MIRANDA |
| Initial Grading | 4/5/2024 | Partial Approval | JOHNNY MIRANDA |
| Initial Grading | 7/24/2025 | Partial Inspection | JOHNNY MIRANDA |
| Bottom/Toe | 10/22/2025 | Approved | JOHNNY MIRANDA |
| FLOOD-Proofing Certificate | 10/22/2025 | Approved | JOHNNY MIRANDA |
| Final | 10/22/2025 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 10/22/2025 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 2/11/2026 | Approved | RUSSELL BONVOULOIR |
| Final | 2/19/2026 | Permit Finaled | RUSSELL BONVOULOIR |