348 S HILGARD AVE 90024
Certificate Information: 348 S HILGARD AVE 90024
- Application / Permit
- 22030-30000-03993
- Plan Check / Job No.
- B22WL01283
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Site Grading
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/24/2025
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 5/10/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 5/23/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/1/2022 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 11/2/2022 | APPLICANT |
| Plan Check Approved | 12/8/2022 | HOOMAN HAJIZADEH |
| Issued | 12/19/2022 | APPLICANT |
| Permit Finaled | 6/23/2025 | LANNY MERRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/1/2022 | FELIPE HERNANDEZ |
Contact Information
| Architect | Davis,, Lisa M; Lic. No.: C27408 | 3242 MALCOLM AVENUE LOS ANGELES, CA 90034 |
| Contractor | Owner-Builder | , |
| Engineer | Lotfi,, Fariborz Frank; Lic. No.: C49359 | 1328 DUENDE LANE PACIFIC PALISADES, CA 90272 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 1/25/2023 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 2/21/2023 | Approved | RUSSELL BONVOULOIR |
| Excavation | 2/21/2023 | Approved | RUSSELL BONVOULOIR |
| Initial Grading | 2/21/2023 | Approved | RUSSELL BONVOULOIR |
| Sub-Drain | 4/7/2023 | Partial Approval | CHARLES POWELL |
| Final | 9/19/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 9/19/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 10/23/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 10/23/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 4/28/2025 | Not Ready for Inspection | AL GAMBLE |
| Final | 5/14/2025 | Not Ready for Inspection | AL GAMBLE |
| Rough | 5/14/2025 | Not Ready for Inspection | AL GAMBLE |
| Approved Compaction Report | 6/12/2025 | Approved | MATTHEW JENKINS |
| Final | 6/23/2025 | Permit Finaled | LANNY MERRICK |
| Rough | 6/23/2025 | Approved | LANNY MERRICK |