3055 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3055 S MOUNTAIN VIEW AVE 90066

Application / Permit
22030-30000-02754
Plan Check / Job No.
B22WL01498
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
grading for new retaining wall
Permit Issued
Issued on 1/3/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 7/19/2024

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 TARIK SAOUD
Corrections Issued 4/25/2022 TARIK SAOUD
Quality Review Completed 4/26/2022 CHIHARU SUZUKI
Applicant returned to address corrections 6/30/2022 TARIK SAOUD
Applicant returned to address corrections 9/6/2022 TARIK SAOUD
Applicant returned to address corrections 10/14/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/17/2022 KAVIAN REFAHI
Building Plans Picked Up 10/17/2022 APPLICANT
Plan Check Approved 11/23/2022 KAVIAN REFAHI
Issued 1/3/2023 APPLICANT
Permit Finaled 7/18/2024 MATTHEW JENKINS

Permit Application Clearance Information

Low Impact Development Cleared 6/14/2022 MARTIN FRAGOSO
Construction near power lines Cleared 10/26/2022 WALTER RAMIREZ
Excavation more than 5-ft deep Cleared 11/23/2022 CALOSHA APPROVED

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Haddad,, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/23/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 2/2/2023 Corrections Issued MATTHEW JENKINS
Bottom/Toe 2/6/2023 Corrections Issued MATTHEW JENKINS
Bottom/Toe 2/10/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 3/8/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 3/16/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 4/10/2023 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 5/10/2023 Partial Approval RUSSELL BONVOULOIR
Rough 6/5/2023 Partial Approval RUSSELL BONVOULOIR
Approved Compaction Report 9/14/2023 Approved RUSSELL BONVOULOIR
Bottom/Toe 10/2/2023 Partial Inspection MATTHEW JENKINS
Final 10/2/2023 Partial Inspection MATTHEW JENKINS
Rough 10/2/2023 Partial Inspection MATTHEW JENKINS
Initial Grading 5/30/2024 Corrections Issued MATTHEW JENKINS
Bottom/Toe 6/3/2024 Partial Inspection MATTHEW JENKINS
Final 6/3/2024 Partial Inspection MATTHEW JENKINS
Rough 6/3/2024 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 7/5/2024 Approved MATTHEW JENKINS
Bottom/Toe 7/18/2024 Approved MATTHEW JENKINS
Final 7/18/2024 Permit Finaled MATTHEW JENKINS
Rough 7/18/2024 Approved MATTHEW JENKINS