1401 N ROSCOMARE ROAD 90077

Certificate Information: 1401 N ROSCOMARE ROAD 90077

Application / Permit
22030-30000-01457
Plan Check / Job No.
B22WL00791
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW RETAINING WALL. COMPLY WITH DEPARTMENT ORDER effective date 04/05/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 924359.
Permit Issued
Issued on 12/5/2022
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 7/21/2023

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 SERGIO SILVA
Corrections Issued 4/6/2022 SERGIO SILVA
Quality Review Completed 4/8/2022 FELIX FIGUEROA
Applicant returned to address corrections 11/4/2022 SERGIO SILVA
Building Plans Picked Up 11/7/2022 APPLICANT
Plan Check Approved 12/5/2022 SERGIO SILVA
Issued 12/5/2022 APPLICANT
Permit Finaled 7/20/2023 CHARLES POWELL

Permit Application Clearance Information

Landscape for retaining wall Cleared 10/11/2022 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 11/4/2022 SERGIO SILVA
Miscellaneous Cleared 11/4/2022 SERGIO SILVA
Excavation more than 5-ft deep Cleared 12/5/2022 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 1/18/2023 Partial Inspection MATTHEW JENKINS
Initial Grading 1/18/2023 Corrections Issued MATTHEW JENKINS
Rough 1/26/2023 Partial Inspection RUSSELL BONVOULOIR
Sub-Drain 4/12/2023 Approved VASIL MIHALEV
Bottom/Toe 5/17/2023 Approved VASIL MIHALEV
Final 5/17/2023 Not Ready for Inspection VASIL MIHALEV
Rough 5/17/2023 Approved VASIL MIHALEV
Sub-Drain 5/17/2023 Approved VASIL MIHALEV
Approved Compaction Report 6/26/2023 Approved CHARLES POWELL
Final 7/20/2023 Permit Finaled CHARLES POWELL