1706 N MANDEVILLE LANE 90049

Certificate Information: 1706 N MANDEVILLE LANE 90049

Application / Permit
22030-30000-00609
Plan Check / Job No.
B22WL00348
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Site grading for (N) SFD, pool & R&R.
Permit Issued
Issued on 3/19/2022
Issuing Office
Current Status
Permit Finaled on 3/1/2024

Permit Application Status History

Submitted 1/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 JAHANSHAH POURHASSAN
Corrections Issued 2/7/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/4/2022 JAHANSHAH POURHASSAN
Plan Check Approved 3/15/2022 JAHANSHAH POURHASSAN
Issued 3/19/2022 APPLICANT
Permit Finaled 3/1/2024 JOHNNY MIRANDA

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Radziner,, Ronald Mark; Lic. No.: C22228 MARMOL RADZINER & ASSOCIATES   12210 NEBRASKA AVE    LOS ANGELES, CA 90025
Contractor Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B 12210 NEBRASKA AVENUE      LOS ANGELES, CA 90025
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Hennon,, Robert David; Lic. No.: L5573 601 E GLENOAKS BLVD 208      GLENDALE, CA 91207
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/24/2022 Corrections Issued MATTHEW JENKINS
Drainage Devices/Catch Basin 3/31/2022 Partial Approval CHARLES POWELL
Initial Grading 3/31/2022 Approved CHARLES POWELL
Bottom/Toe 4/7/2022 Approved CHARLES POWELL
Bottom/Toe 4/14/2022 Partial Approval CHARLES POWELL
FLOOD-Proofing Certificate 4/14/2022 Approved CHARLES POWELL
Fill/Backfill 4/14/2022 Partial Approval CHARLES POWELL
Rough 4/14/2022 Partial Approval CHARLES POWELL
Bottom/Toe 4/22/2022 Approved KIRK LINKLATER
Approved Compaction Report 5/2/2022 Partial Approval CHARLES POWELL
Approved Compaction Report 11/15/2022 Corrections Issued CHARLES POWELL
Final 2/23/2024 Corrections Issued JOHNNY MIRANDA
Rough 2/23/2024 Approved JOHNNY MIRANDA
Final 3/1/2024 Permit Finaled JOHNNY MIRANDA