11201 S MAIN ST 90061

Certificate Information: 11201 S MAIN ST 90061

Application / Permit
22030-20000-08086
Plan Check / Job No.
B21VN00572
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
REMOVE AND RECCOMPACT UNDER THE BUILDING
Permit Issued
Issued on 12/21/2022
Issuing Office
Valley
Current Status
Permit Finaled on 10/9/2025

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 RARES BODEA
Corrections Issued 1/24/2021 RARES BODEA
Disabled Access Plans Picked Up 1/27/2021 APPLICANT
Green Plans Picked Up 1/27/2021 APPLICANT
Quality Review Completed 1/29/2021 STEVEN KIM
Building Plans Picked Up 2/8/2021 APPLICANT
Applicant returned to address corrections 11/23/2022 RARES BODEA
Applicant returned to address corrections 12/15/2022 RARES BODEA
Plan Check Approved 12/21/2022 RARES BODEA
Issued 12/21/2022 APPLICANT
Permit Finaled 10/9/2025 JONATHAN HOM

Permit Application Clearance Information

ZI Cleared 12/19/2022 HELEN JADALI
Redevelopment Project Area Cleared 12/20/2022 DAVID URITA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 12/22/2022 Partial Approval JONATHAN HOM
Deputy Grading 12/29/2022 Approved JONATHAN HOM
Deputy Grading 12/30/2022 Conditional Approval LANNY MERRICK
Deputy Grading 1/6/2023 Conditional Approval LANNY MERRICK
Bottom/Toe 1/12/2023 Corrections Issued JONATHAN HOM
Excavation 1/12/2023 Partial Inspection JONATHAN HOM
Approved Compaction Report 5/15/2023 Partial Approval JONATHAN HOM
Approved Compaction Report 5/26/2023 Approved JONATHAN HOM
Bottom/Toe 6/5/2025 Partial Inspection JONATHAN HOM
Final 6/5/2025 Partial Inspection JONATHAN HOM
Rough 6/5/2025 Partial Inspection JONATHAN HOM
Special/Order Compliance 6/5/2025 Partial Inspection JONATHAN HOM
Bottom/Toe 8/12/2025 Approved JONATHAN HOM
Drainage Devices/Catch Basin 8/12/2025 Approved JONATHAN HOM
Final 8/12/2025 Partial Approval JONATHAN HOM
Irrigation/Landscape 8/12/2025 Approved JONATHAN HOM
Rough 8/12/2025 Approved JONATHAN HOM
Final 10/9/2025 Permit Finaled JONATHAN HOM