8810 N TAMPA AVE 91324
Certificate Information: 8810 N TAMPA AVE 91324
- Application / Permit
- 22030-20000-07482
- Plan Check / Job No.
- B22VN15969
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR PARKING LOT AND COSTCO GAS REFUELING CANOPY.. OVER-X 500CY.
- Permit Issued
- Issued on 2/7/2024
- Issuing Office
- Current Status
- Permit Finaled on 7/8/2024
Permit Application Status History
| Submitted | 10/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | JOE VO |
| Corrections Issued | 10/30/2022 | JOE VO |
| Quality Review Completed | 10/31/2022 | GARO TELMI |
| Plan Check Approved | 2/28/2023 | JOE VO |
| No Progress | 2/5/2024 | JOE VO |
| Plan Check Approved | 2/5/2024 | JOE VO |
| Issued | 2/7/2024 | APPLICANT |
| Permit Finaled | 7/3/2024 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Prkng lot landscape/Water mgmt | Cleared | 2/7/2024 | YINGSHI HUANG |
Contact Information
| Architect | Menard,, Nathan D; Lic. No.: C27019 | 345 W 6TH STREET UNIT A TUSTIN, CA 92780 |
| Contractor | Jones/Covey Group Incorporated; Lic. No.: 804431-B | , |
| Engineer | Grubb,, Hal P; Lic. No.: C67814 | 18215 72ND AVE SOUTH KENT, WA 98032 |
Inspector Information
| ALEXANDER HELFER, (818) 374-4354 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 2/9/2024 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 2/12/2024 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Initial Grading | 2/15/2024 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Initial Grading | 3/21/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Excavation | 3/26/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 4/3/2024 | Partial Inspection | MANUEL TEJADA |
| Excavation | 4/3/2024 | Partial Approval | MANUEL TEJADA |
| Fill/Backfill | 4/3/2024 | Partial Approval | MANUEL TEJADA |
| Fill/Backfill | 4/8/2024 | Approved | ROBERT PINA |
| Sub-Drain | 4/10/2024 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation | 5/1/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 5/9/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 5/15/2024 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Fill/Backfill | 5/23/2024 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 6/10/2024 | Not Ready for Inspection | CHARLES POWELL |
| Private Sewage Disposal System | 6/10/2024 | Not Ready for Inspection | CHARLES POWELL |
| Approved Compaction Report | 6/25/2024 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 7/1/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 7/3/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/3/2024 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |
| Rough | 7/3/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |