13209 W DOBBINS PL 90049
Certificate Information: 13209 W DOBBINS PL 90049
- Application / Permit
- 22030-20000-05351
- Plan Check / Job No.
- B22VN02479
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- NEW GRADING FOR EXCAVATION AND BACKFILL NEW SFD WITH BASEMENT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/5/2024
Permit Application Status History
| Submitted | 3/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | RARES BODEA |
| Corrections Issued | 4/11/2022 | RARES BODEA |
| Quality Review Completed | 4/14/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| Applicant returned to address corrections | 8/1/2022 | RARES BODEA |
| Applicant returned to address corrections | 8/2/2022 | RARES BODEA |
| Plan Check Approved | 8/31/2022 | RARES BODEA |
| Issued | 2/9/2023 | APPLICANT |
| Permit Finaled | 6/3/2024 | JOHNNY MIRANDA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 2/17/2023 | Approved | VASIL MIHALEV |
| Sub-Drain | 4/10/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Special/Order Compliance | 6/26/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 11/21/2023 | Corrections Issued | MATTHEW JENKINS |
| Bottom/Toe | 6/3/2024 | Approved | JOHNNY MIRANDA |
| Final | 6/3/2024 | Permit Finaled | JOHNNY MIRANDA |
| Rough | 6/3/2024 | Approved | JOHNNY MIRANDA |