1936 S THAYER AVE 90025
Certificate Information: 1936 S THAYER AVE 90025
- Application / Permit
- 22030-20000-05091
- Plan Check / Job No.
- B22VN00429
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- EXCAVATION AND BACKFILL FOR NEW RETAILING WALLS AND R&R UNDER THE BUILDING
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/11/2025
Permit Application Status History
| Submitted | 1/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | TROY DEGUZMAN |
| Corrections Issued | 2/9/2022 | TROY DEGUZMAN |
| Quality Review Completed | 2/11/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Applicant returned to address corrections | 4/27/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 7/19/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 9/2/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/10/2022 | MOHAMMAD ESMAILI |
| Issued | 11/10/2022 | APPLICANT |
| Permit Finaled | 2/10/2025 | VASIL MIHALEV |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Cas Construction; Lic. No.: 766810-B | PO BOX 572349 TARZANA, CA 91357 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 12/9/2022 | Corrections Issued | AL GAMBLE |
| Initial Grading | 12/9/2022 | Not Ready for Inspection | AL GAMBLE |
| Special/Order Compliance | 12/14/2022 | Corrections Issued | AL GAMBLE |
| Excavation | 12/21/2022 | Corrections Issued | MATTHEW JENKINS |
| Rough | 1/9/2023 | Partial Approval | MATTHEW JENKINS |
| Fill/Backfill | 1/26/2023 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 1/26/2023 | Partial Approval | MATTHEW JENKINS |
| Excavation | 2/3/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 2/10/2023 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 2/22/2023 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 4/4/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 4/7/2023 | Not Ready for Inspection | CHARLES POWELL |
| Sub-Drain | 4/10/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 4/24/2023 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 7/28/2023 | Approved | CHARLES POWELL |
| Bottom/Toe | 1/28/2025 | Partial Inspection | JOHNNY MIRANDA |
| Final | 1/28/2025 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 1/28/2025 | Partial Inspection | JOHNNY MIRANDA |
| Bottom/Toe | 2/10/2025 | Approved | VASIL MIHALEV |
| Final | 2/10/2025 | Permit Finaled | VASIL MIHALEV |
| Rough | 2/10/2025 | Approved | VASIL MIHALEV |