441 N ROCKINGHAM AVE 90049

Certificate Information: 441 N ROCKINGHAM AVE 90049

Application / Permit
22030-20000-04981
Plan Check / Job No.
B22VN10877
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING PERMIT FOR SITE PREP, EXCAVATION FOR NEW BASEMENT, SHORING, AND RET. WALL BACKFILL
Permit Issued
Issued on 10/14/2022
Issuing Office
Valley
Current Status
Permit Finaled on 5/1/2025

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 SEAN SHAHMIRI
Corrections Issued 8/2/2022 SEAN SHAHMIRI
Quality Review Completed 8/4/2022 OMID HEDAYAT
Building Plans Picked Up 8/5/2022 APPLICANT
Applicant returned to address corrections 9/19/2022 SEAN SHAHMIRI
Plan Check Approved 9/29/2022 SEAN SHAHMIRI
Issued 10/14/2022 APPLICANT
Permit Finaled 4/30/2025 JOHNNY MIRANDA

Permit Application Clearance Information

Watercourse Cleared 8/3/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/4/2022 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 9/29/2022 CALOSHA APPROVED

Contact Information

Contractor Sky Remodeling Inc; Lic. No.: 955109-B 12439 MAGNOLIA BLVD #245      VALLEY VILLAGE, CA 91607
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Tani,, Jason; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/17/2022 Approved CHARLES POWELL
Excavation 10/20/2022 Partial Approval CHARLES POWELL
Excavation 10/25/2022 Not Ready for Inspection CHARLES POWELL
Sub-Drain 1/31/2023 Partial Approval RUSSELL BONVOULOIR
Special/Order Compliance 3/2/2023 Not Ready for Inspection CHARLES POWELL
Bottom/Toe 3/6/2023 Partial Approval CHARLES POWELL
Special/Order Compliance 4/19/2023 Corrections Issued CHARLES POWELL
Approved Compaction Report 5/8/2023 Partial Approval CHARLES POWELL
Approved Compaction Report 10/10/2024 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 10/18/2024 Approved MATTHEW JENKINS
Bottom/Toe 4/4/2025 Partial Inspection MATTHEW JENKINS
Final 4/4/2025 Partial Inspection MATTHEW JENKINS
Rough 4/4/2025 Partial Inspection MATTHEW JENKINS
Bottom/Toe 4/10/2025 Not Ready for Inspection MATTHEW JENKINS
Final 4/10/2025 Corrections Issued MATTHEW JENKINS
Rough 4/10/2025 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 4/17/2025 Approved JOHNNY MIRANDA
Final 4/17/2025 Corrections Issued JOHNNY MIRANDA
Rough 4/17/2025 Approved JOHNNY MIRANDA
Final 4/24/2025 Not Ready for Inspection JOHNNY MIRANDA
Approved Compaction Report 4/29/2025 Approved MATTHEW JENKINS
Final 4/30/2025 Permit Finaled JOHNNY MIRANDA