4929 N MECCA AVE 91356
Certificate Information: 4929 N MECCA AVE 91356
- Application / Permit
- 22030-20000-04311
- Plan Check / Job No.
- B22VN09472
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING EXCAVATION FOR REAR RETAINING WALL & FENCE WALL.
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- Issued on 7/27/2022
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/18/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Applicant returned to address corrections | 7/7/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 7/27/2022 | ARTIN ZARUKIAN |
| Issued | 7/27/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Paradise Creation Inc; Lic. No.: 1017683-B | 17933 TOPHAM ST ENCINO, CA 91316 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 7/28/2022 | Not Ready for Inspection | LANNY MERRICK |
| Rough | 7/29/2022 | Approved | LANNY MERRICK |
| Sub-Drain | 8/4/2022 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 9/1/2022 | Not Ready for Inspection | LANNY MERRICK |
| Bottom/Toe | 6/2/2023 | Corrections Issued | ROBERT PINA |
| Final | 6/2/2023 | Corrections Issued | ROBERT PINA |
| Approved Compaction Report | 11/16/2023 | Approved | ROBERT HUGHES |
| Bottom/Toe | 12/27/2023 | Not Ready for Inspection | ROBERT PINA |
| Final | 12/27/2023 | Not Ready for Inspection | ROBERT PINA |