3400 S GREENWOOD AVE 90066

Certificate Information: 3400 S GREENWOOD AVE 90066

Application / Permit
22030-20000-02716
Plan Check / Job No.
B22VN05690
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
EXCAVATION AND BACKFILL FOR RETAINING WALL, R&R ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/10/2022
Issuing Office
Metro
Current Status
Permit Finaled on 7/18/2024

Permit Application Status History

Submitted 4/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/28/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/9/2022 OMID HEDAYAT
Building Plans Picked Up 5/10/2022 APPLICANT
Applicant returned to address corrections 6/1/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/23/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 11/7/2022 SEWADA ZADOORAN MILAGARDI
Issued 11/10/2022 APPLICANT
Permit Finaled 7/17/2024 MATTHEW JENKINS

Permit Application Clearance Information

ZA Case Cleared 5/3/2022 RICHARD REASER
Grading Pre-Inspection Cleared 11/7/2022 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Hsu,, Peggy P; Lic. No.: C32998 3708 BEVERLY RIDGE DR.      SHERMAN OAKS, CA 91423
Contractor Apex Investment Holdings; Lic. No.: 943202-B 7095 HOLLYWOOD BOULEVARD #1290      LOS ANGELES, CA 90028

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 12/19/2022 Conditional Approval MATTHEW JENKINS
Deputy Grading 12/22/2022 No Access for Inspection MATTHEW JENKINS
Initial Grading 12/22/2022 Corrections Issued MATTHEW JENKINS
Initial Grading 12/28/2022 Partial Approval MATTHEW JENKINS
Initial Grading 1/11/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 1/20/2023 Approved VASIL MIHALEV
Deputy Grading 1/20/2023 Approved VASIL MIHALEV
Rough 2/3/2023 Partial Approval MATTHEW JENKINS
Rough 2/21/2023 Partial Approval RUSSELL BONVOULOIR
Approved Compaction Report 2/22/2023 Partial Inspection AL GAMBLE
Rough 4/10/2023 Not Ready for Inspection VASIL MIHALEV
Fill/Backfill 4/24/2023 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 4/24/2023 Partial Approval RUSSELL BONVOULOIR
Rough 4/28/2023 Conditional Approval RUSSELL BONVOULOIR
Rough 5/19/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 7/16/2024 Approved MATTHEW JENKINS
Rough 7/16/2024 Approved MATTHEW JENKINS
Final 7/17/2024 Permit Finaled MATTHEW JENKINS