1017 N DEXTER ST 90042
Certificate Information: 1017 N DEXTER ST 90042
- Application / Permit
- 22030-20000-01359
- Plan Check / Job No.
- B22VN02966
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR SITE PREP AND BACKFILL FOR NEW RET WALL
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/23/2025
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | COLIN LOREDO |
| Corrections Issued | 3/14/2022 | COLIN LOREDO |
| Quality Review Completed | 3/18/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/27/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 7/7/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 8/11/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 8/24/2022 | SEAN SHAHMIRI |
| Issued | 12/12/2022 | APPLICANT |
| Permit Finaled | 1/22/2025 | LANNY MERRICK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 2/1/2023 | Not Ready for Inspection | LANNY MERRICK |
| Initial Grading | 2/1/2023 | Approved | LANNY MERRICK |
| Bottom/Toe | 8/16/2023 | No Access for Inspection | RUSSELL BONVOULOIR |
| Excavation | 8/16/2023 | No Access for Inspection | RUSSELL BONVOULOIR |
| Excavation | 8/17/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Special/Order Compliance | 8/17/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Bottom/Toe | 8/25/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Final | 8/25/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Rough | 8/25/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Bottom/Toe | 9/27/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Excavation | 9/27/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 9/27/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 11/14/2023 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 11/14/2023 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 11/14/2023 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 12/15/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Sub-Drain | 4/3/2024 | Not Ready for Inspection | LANNY MERRICK |
| Bottom/Toe | 6/14/2024 | Approved | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 6/14/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 6/14/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Rough | 6/14/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Special/Order Compliance | 6/14/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 12/6/2024 | Partial Inspection | LANNY MERRICK |
| Rough | 12/6/2024 | Partial Inspection | LANNY MERRICK |
| Approved Compaction Report | 1/17/2025 | Approved | LANNY MERRICK |
| Final | 1/22/2025 | Permit Finaled | LANNY MERRICK |
| Rough | 1/22/2025 | Approved | LANNY MERRICK |