1120 E 25TH ST 90011

Certificate Information: 1120 E 25TH ST 90011

Application / Permit
22030-20000-01296
Plan Check / Job No.
B22VN02832
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
REMOVAL & RECOMPACTION FOR (N) APT BLDG -- NON HILLSIDE GRADING AREA
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
Permit Finaled on 2/13/2025

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/23/2022 NILOOFAR MEHRAIN
Plan Check Approved 2/23/2022 NILOOFAR MEHRAIN
Issued 3/15/2022 APPLICANT
Permit Finaled 2/12/2025 JONATHAN HOM

Permit Application Clearance Information

"D" conditions Cleared 2/25/2022 DANG NGUYEN
Miscellaneous Cleared 2/25/2022 DANG NGUYEN
Community Plan Implem. Overlay Cleared 2/28/2022 HELEN JADALI
ZI Cleared 2/28/2022 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/21/2022 Approved LANNY MERRICK
Bottom/Toe 4/6/2022 Partial Approval LANNY MERRICK
Excavation 4/6/2022 Partial Approval LANNY MERRICK
Fill/Backfill 4/11/2022 Partial Inspection MATTHEW JENKINS
Bottom/Toe 4/12/2022 Partial Approval MATTHEW JENKINS
Approved Compaction Report 4/21/2022 Partial Inspection MATTHEW JENKINS
Initial Grading 4/21/2022 Partial Approval MATTHEW JENKINS
Bottom/Toe 4/26/2022 Partial Inspection MATTHEW JENKINS
Deputy Grading 4/26/2022 Conditional Approval MATTHEW JENKINS
Excavation 4/26/2022 Partial Approval MATTHEW JENKINS
Deputy Grading 4/27/2022 No Access for Inspection MATTHEW JENKINS
Bottom/Toe 4/29/2022 Partial Approval KIRK LINKLATER
Deputy Grading 5/3/2022 Approved JONATHAN HOM
Fill/Backfill 5/9/2022 Not Ready for Inspection MATTHEW JENKINS
Rough 5/9/2022 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 5/17/2022 Approved ROBERT HUGHES
Bottom/Toe 1/30/2025 Not Ready for Inspection JONATHAN HOM
Final 1/30/2025 Corrections Issued JONATHAN HOM
Rough 1/30/2025 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 2/11/2025 Partial Inspection JONATHAN HOM
Final 2/11/2025 Partial Inspection JONATHAN HOM
Rough 2/11/2025 Partial Inspection JONATHAN HOM
Approved Compaction Report 2/12/2025 Approved JONATHAN HOM
Bottom/Toe 2/12/2025 Approved JONATHAN HOM
Final 2/12/2025 Permit Finaled JONATHAN HOM
Rough 2/12/2025 Approved JONATHAN HOM