1120 E 25TH ST 90011
Certificate Information: 1120 E 25TH ST 90011
- Application / Permit
- 22030-20000-01296
- Plan Check / Job No.
- B22VN02832
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- REMOVAL & RECOMPACTION FOR (N) APT BLDG -- NON HILLSIDE GRADING AREA
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/13/2025
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/23/2022 | NILOOFAR MEHRAIN |
| Issued | 3/15/2022 | APPLICANT |
| Permit Finaled | 2/12/2025 | JONATHAN HOM |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/25/2022 | DANG NGUYEN |
| Miscellaneous | Cleared | 2/25/2022 | DANG NGUYEN |
| Community Plan Implem. Overlay | Cleared | 2/28/2022 | HELEN JADALI |
| ZI | Cleared | 2/28/2022 | HELEN JADALI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/21/2022 | Approved | LANNY MERRICK |
| Bottom/Toe | 4/6/2022 | Partial Approval | LANNY MERRICK |
| Excavation | 4/6/2022 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 4/11/2022 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 4/12/2022 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 4/21/2022 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 4/21/2022 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 4/26/2022 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 4/26/2022 | Conditional Approval | MATTHEW JENKINS |
| Excavation | 4/26/2022 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 4/27/2022 | No Access for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 4/29/2022 | Partial Approval | KIRK LINKLATER |
| Deputy Grading | 5/3/2022 | Approved | JONATHAN HOM |
| Fill/Backfill | 5/9/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 5/9/2022 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 5/17/2022 | Approved | ROBERT HUGHES |
| Bottom/Toe | 1/30/2025 | Not Ready for Inspection | JONATHAN HOM |
| Final | 1/30/2025 | Corrections Issued | JONATHAN HOM |
| Rough | 1/30/2025 | Not Ready for Inspection | JONATHAN HOM |
| Bottom/Toe | 2/11/2025 | Partial Inspection | JONATHAN HOM |
| Final | 2/11/2025 | Partial Inspection | JONATHAN HOM |
| Rough | 2/11/2025 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 2/12/2025 | Approved | JONATHAN HOM |
| Bottom/Toe | 2/12/2025 | Approved | JONATHAN HOM |
| Final | 2/12/2025 | Permit Finaled | JONATHAN HOM |
| Rough | 2/12/2025 | Approved | JONATHAN HOM |