10950 W VERANO ROAD 90077

Certificate Information: 10950 W VERANO ROAD 90077

Application / Permit
22030-20000-01092
Plan Check / Job No.
B22VN02401
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
EXCAVATION FOR (N) SFD W/ ATTACHED GARAGE & BASEMENT AND EXCAVATION/BACKFILL FOR TWO (N) RETAINING WALLS -- HILLSIDE GRADING AREA
Permit Issued
Issued on 12/20/2022
Issuing Office
Valley
Current Status
Permit Finaled on 2/4/2025

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 COLIN LOREDO
Corrections Issued 2/28/2022 COLIN LOREDO
Quality Review Completed 3/2/2022 OMID HEDAYAT
Building Plans Picked Up 3/3/2022 APPLICANT
Applicant returned to address corrections 9/9/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/7/2022 NILOOFAR MEHRAIN
Plan Check Approved 12/16/2022 NILOOFAR MEHRAIN
Issued 12/20/2022 APPLICANT
Permit Finaled 2/3/2025 MATTHEW JENKINS

Permit Application Clearance Information

GPI Written Notices Cleared 12/16/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 12/16/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sub-Drain 5/19/2023 Approved VASIL MIHALEV
Bottom/Toe 7/27/2023 Approved VASIL MIHALEV
Excavation 8/9/2023 Approved VASIL MIHALEV
Approved Compaction Report 10/26/2023 Corrections Issued CHARLES POWELL
Approved Compaction Report 11/13/2023 Partial Approval CHARLES POWELL
Approved Compaction Report 9/23/2024 Approved VASIL MIHALEV
Final 11/6/2024 Not Ready for Inspection JOHNNY MIRANDA
Rough 11/6/2024 Approved JOHNNY MIRANDA
Final 12/24/2024 Corrections Issued MATTHEW JENKINS
Final 2/3/2025 Permit Finaled MATTHEW JENKINS