3300 W WASHINGTON BLVD 90018
Certificate Information: 3300 W WASHINGTON BLVD 90018
- Application / Permit
- 22030-10000-08850
- Plan Check / Job No.
- B22LA26179
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ePLAN. SITE GRADING FOR NEW APARTMENT, REMOVE AND RECOMPACT
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/20/2026
Permit Application Status History
| Submitted | 1/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | VU NGUYEN |
| Corrections Issued | 2/22/2023 | VU NGUYEN |
| Quality Review Completed | 2/22/2023 | EUGENE BARBEAU |
| Plan Check Approved | 11/2/2023 | VU NGUYEN |
| Issued | 11/2/2023 | APPLICANT |
| Permit Finaled | 2/19/2026 | AL GAMBLE |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 6/1/2023 | TREVOR QUAN |
| Historic Resource Verification | Cleared | 6/29/2023 | MAX LODER |
| Community Plan Implem. Overlay | Cleared | 7/1/2023 | TINA MIRANDA |
| Community Plan Implem. Overlay | Cleared | 8/1/2023 | MOHAMMAD HASAN |
| Miscellaneous | Cleared | 8/21/2023 | ELIZABETH GALLARDO |
| Redevelopment Project Area | Cleared | 8/21/2023 | ELIZABETH GALLARDO |
| Community Plan Implem. Overlay | Cleared | 8/30/2023 | ADALBERTO VERA |
| Excavation more than 5-ft deep | Cleared | 9/6/2023 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2023 | CHRISTINA BRACO |
| Stormwater Pollution Mitigatn | Cleared | 9/12/2023 | MARTIN FRAGOSO |
| Community Plan Implem. Overlay | Cleared | 10/4/2023 | KYLE WINSTON |
| Miscellaneous | Cleared | 10/4/2023 | KYLE WINSTON |
| ZA Case | Cleared | 10/4/2023 | EDBER MACEDO |
| Work Adjacent to Public Way | Cleared | 10/5/2023 | LARRY LEE |
Contact Information
| Contractor | Benchmark Contractors Inc; Lic. No.: 462263-B | 3330 OCEAN PARK BLVD SANTA MONICA, CA 90405 |
| Engineer | Cunningham,, William; Lic. No.: NA80129 | , |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 11/14/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Initial Grading | 11/30/2023 | Partial Approval | JONATHAN HOM |
| Initial Grading | 12/15/2023 | Partial Inspection | JONATHAN HOM |
| Excavation | 2/15/2024 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 2/15/2024 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 3/1/2024 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 3/6/2024 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 3/8/2024 | Partial Inspection | JONATHAN HOM |
| Rough | 3/11/2024 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 3/12/2024 | Approved | JONATHAN HOM |
| Deputy Grading | 3/13/2024 | Approved | JONATHAN HOM |
| Bottom/Toe | 3/14/2024 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 3/14/2024 | Approved | JONATHAN HOM |
| Rough | 3/14/2024 | Partial Inspection | JONATHAN HOM |
| Deputy Grading | 3/15/2024 | Approved | JONATHAN HOM |
| Bottom/Toe | 3/26/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 4/2/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/17/2024 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 4/26/2024 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 5/7/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 5/16/2024 | Partial Inspection | JONATHAN HOM |
| Rough | 6/25/2024 | Partial Inspection | JONATHAN HOM |
| Fill/Backfill | 7/9/2024 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 8/2/2024 | Approved | JONATHAN HOM |
| Approved Compaction Report | 8/7/2024 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 10/18/2024 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 10/28/2024 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 11/4/2024 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 7/18/2025 | Partial Inspection | JONATHAN HOM |
| Rough | 7/18/2025 | Partial Inspection | JONATHAN HOM |
| Rough | 8/1/2025 | Partial Inspection | JONATHAN HOM |
| Special/Order Compliance | 9/9/2025 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 10/9/2025 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 11/4/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 2/19/2026 | Approved | AL GAMBLE |
| Final | 2/19/2026 | Permit Finaled | AL GAMBLE |
| Rough | 2/19/2026 | Approved | AL GAMBLE |