8353 N SEPULVEDA BLVD 91343

Certificate Information: 8353 N SEPULVEDA BLVD 91343

Application / Permit
22030-10000-08688
Plan Check / Job No.
B22LA25687
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING WORK FOR CONSTRUCTION OF NEW TWO STORY MAZDA DEALERSHIP WITH SHOWROOM, SERVICE BAYS AND PART STORAGE. PARKING PROVIDED WILL BE PER AB2097 (21AUTOMOBILE PARKING WILL BE PROVIDED) NEW DRAINGE SYSTEM AND REGRADING OF THE SITE
Permit Issued
Issued on 10/15/2025
Issuing Office
Metro
Current Status
Issued on 10/15/2025

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Green Plans Picked Up 1/23/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 MINA HABIB
Corrections Issued 3/7/2023 MINA HABIB
Quality Review Completed 3/9/2023 RODOLFO ARIAS
Building Plans Picked Up 3/17/2023 APPLICANT
Disabled Access Plans Picked Up 3/31/2023 APPLICANT
Applicant returned to address corrections 2/22/2024 MINA HABIB
Applicant returned to address corrections 8/29/2024 MINA HABIB
Applicant returned to address corrections 9/6/2024 MINA HABIB
Applicant returned to address corrections 1/21/2025 MINA HABIB
Applicant returned to address corrections 1/30/2025 MINA HABIB
Applicant returned to address corrections 2/13/2025 MINA HABIB
Applicant returned to address corrections 2/20/2025 MINA HABIB
Applicant returned to address corrections 3/18/2025 MINA HABIB
Applicant returned to address corrections 3/27/2025 MINA HABIB
Applicant returned to address corrections 4/15/2025 MINA HABIB
Applicant returned to address corrections 5/8/2025 MINA HABIB
Applicant returned to address corrections 5/20/2025 MINA HABIB
Applicant returned to address corrections 5/23/2025 MINA HABIB
Applicant returned to address corrections 6/11/2025 MINA HABIB
Applicant returned to address corrections 6/17/2025 MINA HABIB
Plan Check Approved 10/9/2025 MINA HABIB
Issued 10/15/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/30/2023 CARLOS AGUILERA
Construction near power lines Cleared 3/15/2025 TINA MIRANDA
Construction within easement Cleared 3/15/2025 TINA MIRANDA
Low Impact Development (LID) Cleared 6/16/2025 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/30/2025 BRYAN GODINEZ
Excavation more than 5-ft deep Cleared 8/8/2025 CALOSHA APPROVED

Contact Information

Contractor Kunzik & Sara Construction Inc; Lic. No.: 847939-B 1699 LA COSTA MEADOWS DR #102      SAN MARCOS, CA 92078
Engineer Albertson,, Aaron Marcus; Lic. No.: C65513 2 WAYSIDE      NEWPORT BEACH, CA 92657

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/23/2025 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Initial Grading 10/28/2025 Approved GERMAN RODRIGUEZ MENDOZA
SWPPP-Const. Storm Water 10/28/2025 Completed GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 12/1/2025 Approved ALEXANDER HELFER
Fill/Backfill 12/3/2025 Approved ALEXANDER HELFER
Fill/Backfill 12/8/2025 Approved ALEXANDER HELFER
Fill/Backfill 12/10/2025 Approved ALEXANDER HELFER
Bottom/Toe 12/15/2025 Partial Approval CHARLES POWELL
Fill/Backfill 12/16/2025 Approved ALEXANDER HELFER
Fill/Backfill 12/18/2025 Approved ALEXANDER HELFER
Fill/Backfill 12/23/2025 Approved ALEXANDER HELFER
Approved Compaction Report 2/2/2026 Approved ALEXANDER HELFER