3757-3759 S DALTON AVE 90018
Certificate Information: 3757-3759 S DALTON AVE 90018
- Application / Permit
- 22030-10000-08151
- Plan Check / Job No.
- B22LA06066
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR NEW DUPLEX UNDER 22010-10000-01725. REMOVAL & RECOMPACT 665 C.Y.
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/20/2024
Permit Application Status History
| Submitted | 4/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 4/26/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 4/27/2022 | PETER KIM |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Applicant returned to address corrections | 9/7/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/20/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 11/4/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 11/29/2022 | ARMEN JIVALAGIAN |
| Issued | 3/10/2023 | APPLICANT |
| Permit Finaled | 11/19/2024 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Hold | Cleared | 4/14/2023 | MARIA VENDIVIL |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 5/19/2023 | Partial Inspection | JONATHAN HOM |
| Excavation | 5/23/2023 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 5/31/2023 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 6/6/2023 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 6/6/2023 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 6/29/2023 | Partial Approval | JONATHAN HOM |
| Fill/Backfill | 6/29/2023 | Corrections Issued | JONATHAN HOM |
| Approved Compaction Report | 9/6/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 9/6/2023 | Approved | JONATHAN HOM |
| Bottom/Toe | 10/16/2024 | Approved | JONATHAN HOM |
| Final | 10/16/2024 | Corrections Issued | JONATHAN HOM |
| Rough | 10/16/2024 | Approved | JONATHAN HOM |
| Final | 11/19/2024 | Permit Finaled | RUSSELL BONVOULOIR |