501 N LATIMER ROAD 90402
Certificate Information: 501 N LATIMER ROAD 90402
- Application / Permit
- 22030-10000-07957
- Plan Check / Job No.
- B22LA23396
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING, REMOVAL & RECOMPACTION FOR ADDITION & REMODEL TO (E) SINGLE FAMILY DWELLING & (N) 2 STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/1/2025
Permit Application Status History
| Issued | 12/1/2022 | APPLICANT |
| Permit Finaled | 4/30/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/18/2022 | TIMOTHY POWELL |
| Miscellaneous | Cleared | 11/29/2022 | LAMAR DAVIS |
Contact Information
| Contractor | Tm Design Build; Lic. No.: 1068098-B | 27475 YNEZ RD #349 TEMECULA, CA 92591 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 12/2/2022 | Partial Approval | MICHAEL TEMPLE |
| Initial Grading | 12/2/2022 | Approved | MICHAEL TEMPLE |
| Approved Compaction Report | 12/20/2022 | Approved | RUSSELL BONVOULOIR |
| Excavation | 12/20/2022 | Approved | RUSSELL BONVOULOIR |
| Excavation | 1/25/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 1/27/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 3/24/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 3/24/2023 | Approved | RUSSELL BONVOULOIR |
| Approved Compaction Report | 4/15/2025 | Corrections Issued | JOHNNY MIRANDA |
| Bottom/Toe | 4/15/2025 | Approved | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 4/15/2025 | Approved | JOHNNY MIRANDA |
| Excavation | 4/15/2025 | Approved | JOHNNY MIRANDA |
| Final | 4/15/2025 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 4/15/2025 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 4/30/2025 | Approved | JOHNNY MIRANDA |