2801 N OAK POINT DR 90068
Certificate Information: 2801 N OAK POINT DR 90068
- Application / Permit
- 22030-10000-07894
- Plan Check / Job No.
- B22LA23227
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR EXCAVATE AND BACKFILL RETAINING WALL
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/13/2025
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | SAM CHANG |
| Corrections Issued | 12/21/2022 | SAM CHANG |
| Quality Review Completed | 12/23/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/17/2023 | SAM CHANG |
| Applicant returned to address corrections | 5/29/2024 | SAM CHANG |
| Applicant returned to address corrections | 7/31/2024 | SAM CHANG |
| Plan Check Approved | 8/2/2024 | SAM CHANG |
| Issued | 8/20/2024 | APPLICANT |
| Permit Finaled | 8/12/2025 | ALEXANDER HELFER |
Permit Application Clearance Information
| CPC | Cleared | 2/2/2023 | DANIEL CORONADO |
| CPC | Cleared | 2/2/2023 | DANIEL CORONADO |
| Specific Plan | Cleared | 6/5/2024 | TIFFANY CORRALES |
| Specific Plan | Cleared | 6/5/2024 | TIFFANY CORRALES |
| ZI | Cleared | 6/5/2024 | TIFFANY CORRALES |
Contact Information
| Contractor | Blue Pacific Contractors Inc; Lic. No.: 1022139-B | 26211 VALLEY POINT LANE SANTA CLARITA, CA 91321 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/26/2024 | Approved | MANUEL TEJADA |
| Bottom/Toe | 10/8/2024 | Corrections Issued | MANUEL TEJADA |
| Bottom/Toe | 10/15/2024 | Partial Approval | MANUEL TEJADA |
| Rough | 10/22/2024 | Conditional Approval | MANUEL TEJADA |
| Fill/Backfill | 10/29/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 11/20/2024 | Partial Approval | CHARLES POWELL |
| Rough | 11/26/2024 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 12/3/2024 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 12/13/2024 | Approved | MANUEL TEJADA |
| Rough | 12/20/2024 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 12/27/2024 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 7/21/2025 | Approved | CHARLES POWELL |
| Final | 8/12/2025 | Permit Finaled | ALEXANDER HELFER |
| Rough | 8/12/2025 | Approved | ALEXANDER HELFER |