3719 N BUENA PARK DR 91604
Certificate Information: 3719 N BUENA PARK DR 91604
- Application / Permit
- 22030-10000-07869
- Plan Check / Job No.
- B22LA22242
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan - grading, removal and recompaction for SFD w/ basement garage and retaining wall
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- Issued on 12/5/2024
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2022 | KELVIN CHUONG |
| Corrections Issued | 11/10/2022 | KELVIN CHUONG |
| Quality Review Completed | 11/15/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/12/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 8/2/2023 | KELVIN CHUONG |
| Plan Check Approved | 6/17/2024 | KELVIN CHUONG |
| Issued | 12/5/2024 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/1/2023 | KELVIN CHUONG |
| Grading Pre-Inspection | Cleared | 8/1/2023 | KELVIN CHUONG |
Contact Information
| Contractor | Arzuman Brothers Inc; Lic. No.: 1000512-B | PO BOX 1123 GLENDALE, CA 91209 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: NA66957 | , |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sub-Drain | 12/12/2024 | Corrections Issued | MANUEL TEJADA |
| Initial Grading | 12/17/2024 | Approved | MANUEL TEJADA |
| Deputy Grading | 1/21/2025 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 1/28/2025 | Approved | MANUEL TEJADA |
| Excavation | 1/28/2025 | Partial Approval | MANUEL TEJADA |
| Deputy Grading | 1/29/2025 | Approved | MANUEL TEJADA |
| Excavation | 1/29/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Deputy Grading | 1/30/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Other (see comments) | 1/30/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Excavation | 1/30/2025 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 1/31/2025 | Approved | MANUEL TEJADA |
| Excavation | 1/31/2025 | Approved | MANUEL TEJADA |
| Initial Grading | 2/4/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 6/24/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/25/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/26/2025 | Conditional Approval | ALEXANDER HELFER |
| Fill/Backfill | 6/30/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/30/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/31/2025 | Conditional Approval | ALEXANDER HELFER |