1574 N SANBORN AVE 90027
Certificate Information: 1574 N SANBORN AVE 90027
- Application / Permit
- 22030-10000-07848
- Plan Check / Job No.
- B20LA11615
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Site Grading for Proposed addition under the permit 20014-10000-02754.
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/31/2023
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2020 | RICARDO RAMIREZ |
| Corrections Issued | 7/6/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 7/20/2020 | APPLICANT |
| Applicant returned to address corrections | 11/21/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 11/23/2022 | MINA HABILI |
| Issued | 12/15/2022 | APPLICANT |
| Permit Finaled | 8/30/2023 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/19/2020 | ALEXANDER HELFER |
| ZA Case | Cleared | 11/15/2022 | SHASHA YU |
| Excavation more than 5-ft deep | Cleared | 11/23/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Wiltren Contractors Inc; Lic. No.: 974445-B | 8939 S SEPULVEDA BL #110 LOS ANGELES, CA 90045 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/19/2022 | Approved | LANNY MERRICK |
| Initial Grading | 12/22/2022 | Not Ready for Inspection | LANNY MERRICK |
| Bottom/Toe | 12/27/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 12/28/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 1/13/2023 | Not Ready for Inspection | LANNY MERRICK |
| Bottom/Toe | 2/7/2023 | Partial Approval | ALEXANDER HELFER |
| Sub-Drain | 2/9/2023 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 3/8/2023 | Approved | LANNY MERRICK |
| Drainage Devices/Catch Basin | 3/8/2023 | Approved | LANNY MERRICK |
| Drainage Devices/Catch Basin | 4/5/2023 | Partial Approval | LANNY MERRICK |
| Excavation | 4/5/2023 | Partial Approval | LANNY MERRICK |
| Excavation | 4/24/2023 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 4/24/2023 | Partial Approval | LANNY MERRICK |
| Final | 8/30/2023 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 8/30/2023 | Approved | RUSSELL BONVOULOIR |