4120 W MARATHON ST 90029

Certificate Information: 4120 W MARATHON ST 90029

Application / Permit
22030-10000-07692
Plan Check / Job No.
B22LA22617
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
EPLAN ** Sitework grading and drainage associated with existing playground reconstruction/renovation and existing parking lot renovation. OPEN PERMIT 22016-10000-23893
Permit Issued
Issued on 7/17/2023
Issuing Office
Current Status
Permit Finaled on 10/30/2025

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 JOHNNY WU
Corrections Issued 1/4/2023 JOHNNY WU
Quality Review Completed 1/5/2023 RODOLFO ARIAS
Applicant returned to address corrections 2/27/2023 JOHNNY WU
Applicant returned to address corrections 4/10/2023 JOHNNY WU
Plan Check Approved 4/10/2023 JOHNNY WU
Issued 7/17/2023 APPLICANT
Permit Finaled 10/29/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/17/2023 KIRK LINKLATER
Specific Plan Cleared 2/23/2023 DANALYNN DOMINGUEZ
ZA Case Cleared 2/23/2023 RUBEN VASQUEZ
ZA Case Cleared 2/23/2023 RUBEN VASQUEZ
ZI Cleared 2/23/2023 DANALYNN DOMINGUEZ
Low Impact Development Cleared 3/14/2023 TA ANH

Contact Information

Architect Leu,, Mun C; Lic. No.: NA19763       ,
Contractor The Nazerian Group; Lic. No.: 787198-B       ,
Engineer Govil,, Sanjay; Lic. No.: GE2382 4 TULAROSA COURT      ALISO VIEJO, CA 92656
Engineer Tran,, Thomas Minh; Lic. No.: C82464 919 W. GLENOAKS BLVD., 2ND FLOOR      GLENDALE, CA 91202

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 9/20/2023 Corrections Issued RUSSELL BONVOULOIR
Bottom/Toe 9/22/2023 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 9/26/2023 Partial Approval ALEXANDER HELFER
Rough 9/28/2023 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 10/5/2023 Partial Inspection RUSSELL BONVOULOIR
Rough 10/6/2023 Not Ready for Inspection ALEXANDER HELFER
Bottom/Toe 10/11/2023 Approved RUSSELL BONVOULOIR
Sub-Drain 11/2/2023 Partial Inspection RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 1/16/2024 Corrections Issued ALEXANDER HELFER
Sub-Drain 1/16/2024 Not Ready for Inspection ALEXANDER HELFER
Final 8/6/2025 Corrections Issued RUSSELL BONVOULOIR
Rough 8/6/2025 Not Ready for Inspection RUSSELL BONVOULOIR
Approved Compaction Report 10/28/2025 Approved RUSSELL BONVOULOIR
Final 10/29/2025 Permit Finaled RUSSELL BONVOULOIR
Rough 10/29/2025 Approved RUSSELL BONVOULOIR