916 N CHAUTAUQUA BLVD 90272
Certificate Information: 916 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 22030-10000-07457
- Plan Check / Job No.
- B22LA21230
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan - grading for pool/spa 4 of 5
- Permit Issued
- Issued on 2/3/2024
- Issuing Office
- Current Status
- Issued on 2/3/2024
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | KELVIN CHUONG |
| Corrections Issued | 10/31/2022 | KELVIN CHUONG |
| Quality Review Completed | 11/4/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/27/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/18/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/23/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/13/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/22/2023 | KELVIN CHUONG |
| Plan Check Approved | 10/5/2023 | KELVIN CHUONG |
| No Progress | 12/15/2023 | KELVIN CHUONG |
| Plan Check Approved | 12/15/2023 | KELVIN CHUONG |
| Issued | 2/3/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/14/2023 | KIRK LINKLATER |
| Excavation more than 5-ft deep | Cleared | 5/18/2023 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 5/30/2023 | ERNEST TSE |
| GPI Written Notices | Cleared | 5/31/2023 | KELVIN CHUONG |
Contact Information
| Architect | Ogosta,, Edward Thomas; Lic. No.: C30480 | 11157 BARMAN AVENUE CULVER CITY, CA 90230 |
| Architect | Ogosta,, Edward Thomas; Lic. No.: NA30480 | , |
| Contractor | Rigo'S Construction Inc; Lic. No.: 853575-B | P O BOX 922918 SYLMAR, CA 913922918 |
| Engineer | Howe,, Carl William; Lic. No.: NA44773 | , |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 3/5/2024 | Partial Approval | JOHNNY MIRANDA |
| Fill/Backfill | 3/5/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 11/15/2024 | Corrections Issued | VASIL MIHALEV |
| Excavation | 11/15/2024 | Approved | VASIL MIHALEV |