425 S TOWNE AVE 90013
Certificate Information: 425 S TOWNE AVE 90013
- Application / Permit
- 22030-10000-07110
- Plan Check / Job No.
- G22LA00140
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for a new 7 story, 175-unit, 100% affordable housing apartment to include 5 stories of Type IIIA apartment over 1 story Type IA apartment over 1 story Type IA commercial over 1 level Type IA subterranean parking.
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/14/2025
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | VU NGUYEN |
| Corrections Issued | 11/3/2022 | VU NGUYEN |
| Plan Check Approved | 3/29/2023 | VU NGUYEN |
| Issued | 4/26/2023 | APPLICANT |
| Permit Finaled | 7/14/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/10/2023 | ANDRES COVARRUBIAS |
| Historic Resource Verification | Cleared | 1/30/2023 | MAX LODER |
| "Q" conditions | Cleared | 2/1/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 2/1/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 2/1/2023 | NELSON RODRIGUEZ |
| Redevelopment Project Area | Cleared | 2/1/2023 | NELSON RODRIGUEZ |
| "T" removal | Cleared | 2/20/2023 | NATHAN ROMINE |
| CPC | Cleared | 2/21/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 2/21/2023 | NATHAN ROMINE |
| Excavation more than 5-ft deep | Cleared | 3/29/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Benchmark Contractors Inc; Lic. No.: 462263-B | 3330 OCEAN PARK BLVD SANTA MONICA, CA 90405 |
| Engineer | Krief,, Dan D; Lic. No.: NA76041 | , |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/23/2023 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 8/11/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Excavation | 8/11/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 8/28/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 8/30/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 8/31/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 8/31/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 9/5/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 10/3/2023 | Partial Inspection | JONATHAN HOM |
| Fill/Backfill | 10/3/2023 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 10/3/2023 | Conditional Approval | JONATHAN HOM |
| Bottom/Toe | 10/4/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Fill/Backfill | 10/6/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 10/6/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 10/10/2023 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 10/13/2023 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 10/13/2023 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 10/16/2023 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 10/23/2023 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 11/6/2023 | Conditional Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 12/13/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 12/20/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Fill/Backfill | 4/2/2024 | Not Ready for Inspection | LANNY MERRICK |
| Fill/Backfill | 2/4/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Fill/Backfill | 2/19/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 2/27/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Fill/Backfill | 2/27/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 2/28/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Fill/Backfill | 2/28/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 2/28/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 7/10/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Final | 7/10/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Rough | 7/10/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 7/14/2025 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 7/14/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 7/14/2025 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 7/14/2025 | Approved | RUSSELL BONVOULOIR |