6901 S WESTERN AVE 90047
Certificate Information: 6901 S WESTERN AVE 90047
- Application / Permit
- 22030-10000-06792
- Plan Check / Job No.
- B22LA17449
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Site grading/Remove and Recompact for a new apartment building under a building permit application no. 22010-10000-03579. (mod. approved d.d 06/23/2023)
- Permit Issued
- Issued on 6/26/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/26/2026
Permit Application Status History
| Submitted | 9/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | KESETE HAREGOT |
| Corrections Issued | 10/6/2022 | KESETE HAREGOT |
| Quality Review Completed | 10/6/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/13/2022 | KESETE HAREGOT |
| Plan Check Approved | 6/23/2023 | KESETE HAREGOT |
| Plan Check Approved | 6/23/2023 | KESETE HAREGOT |
| Issued | 6/26/2023 | APPLICANT |
| Permit Finaled-Status Void | 1/21/2026 | AL GAMBLE |
| Re-Activate Permit | 2/26/2026 | AL GAMBLE |
| Permit Finaled | 2/26/2026 | MICHAEL TEMPLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2023 | TREVOR QUAN |
| Low Impact Development | Cleared | 4/25/2023 | JORGE MEJIA LEMUS |
| Community Plan Implem. Overlay | Cleared | 5/10/2023 | RAFAEL FONTES |
| Work Adjacent to Public Way | Cleared | 5/17/2023 | ROBIN ETNIEL |
| Excavation more than 5-ft deep | Cleared | 6/23/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Mohrsaz Mike; Lic. No.: 910443-B | 5080 AVENIDA HACIENDA TARZANA, CA 91356 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/28/2023 | Approved | JONATHAN HOM |
| Excavation | 6/29/2023 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 7/3/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 7/6/2023 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 7/6/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 7/7/2023 | Approved | JONATHAN HOM |
| Bottom/Toe | 7/11/2023 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 8/8/2023 | Partial Inspection | JONATHAN HOM |
| Final | 8/8/2023 | Partial Inspection | JONATHAN HOM |
| Rough | 8/8/2023 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 8/8/2023 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 10/9/2025 | Corrections Issued | JONATHAN HOM |
| Irrigation/Landscape | 10/9/2025 | Corrections Issued | JONATHAN HOM |
| Drainage Devices/Catch Basin | 10/10/2025 | Partial Approval | JONATHAN HOM |
| Approved Compaction Report | 1/15/2026 | Approved | JONATHAN HOM |
| Bottom/Toe | 1/15/2026 | Partial Inspection | JONATHAN HOM |
| Final | 1/15/2026 | Corrections Issued | JONATHAN HOM |
| Rough | 1/15/2026 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 1/21/2026 | Approved | AL GAMBLE |
| Final | 1/21/2026 | Partial Inspection | AL GAMBLE |
| Rough | 1/21/2026 | Approved | AL GAMBLE |
| Final | 2/26/2026 | Permit Finaled | MICHAEL TEMPLE |