3400 S BUTLER AVE 90066
Certificate Information: 3400 S BUTLER AVE 90066
- Application / Permit
- 22030-10000-06758
- Plan Check / Job No.
- B22LA19725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 2nd flr addition to (e) 1-story SFD
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | KELVIN CHUONG |
| Corrections Issued | 10/17/2022 | KELVIN CHUONG |
| Quality Review Completed | 10/18/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/15/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 2/22/2023 | KELVIN CHUONG |
| Plan Check Approved | 3/22/2023 | KELVIN CHUONG |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 11/7/2024 | DANIEL VERA |
| CofO Issued | 11/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/25/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 10/25/2022 | DINAH GARIN |
| Miscellaneous | Cleared | 11/1/2022 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 11/1/2022 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 11/1/2022 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 12/2/2022 | GILBERT URREA |
| Specific Plan | Cleared | 12/19/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 2/2/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/3/2023 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 3/22/2023 | KELVIN CHUONG |
Contact Information
| Architect | Bornstein,, Jesse Jordan; Lic. No.: C25216 | 417 BAY STREET #4 SANTA MONICA, CA 90405 |
| Contractor | Bornarch Inc; Lic. No.: 883199-B | 417 BAY STREET #4 SANTA MONICA, CA 90405 |
| Engineer | Padilla,, Juan Carlos; Lic. No.: C79760 | 647 ERBES ROAD THOUSAND OAKS, CA 91362 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/17/2023 | Conditional Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 9/11/2023 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 9/11/2023 | Partial Approval | JESUS PINEDA |
| Pre-Inspection | 9/11/2023 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 9/11/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 9/19/2023 | Approved | JESUS PINEDA |
| Deputy Drilled-In Anchors | 10/3/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 10/4/2023 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 10/4/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 10/10/2023 | Partial Approval | JESUS PINEDA |
| Sewer | 10/10/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 10/10/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | JESUS PINEDA |
| Insulation | 10/18/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/11/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/11/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 3/11/2024 | Approved | JESUS PINEDA |
| Insulation | 4/1/2024 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/1/2024 | Partial Approval | JESUS RODRIGUEZ |
| Shower Pan | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/29/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 4/29/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/29/2024 | Approved | JESUS PINEDA |
| Insulation | 5/2/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/29/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/1/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/1/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 8/1/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/1/2024 | Approved | JESUS PINEDA |
| Final | 10/15/2024 | Corrections Issued | DANIEL VERA |
| Green Building Final | 10/15/2024 | Approved | DANIEL VERA |
| HVAC-Final | 10/15/2024 | Approved | DANIEL VERA |
| Final | 11/7/2024 | OK to Issue CofO | DANIEL VERA |