845 N RADCLIFFE AVE 90272
Certificate Information: 845 N RADCLIFFE AVE 90272
- Application / Permit
- 22030-10000-06709
- Plan Check / Job No.
- B22LA13124
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for ADU addition to SFD 160 CY CUT
- Permit Issued
- Issued on 9/14/2023
- Issuing Office
- Current Status
- Issued on 9/14/2023
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 7/23/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/5/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 9/29/2022 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 10/25/2022 | MARCELA FRANQUEZ |
| Plan Check Approved | 11/18/2022 | MARCELA FRANQUEZ |
| Issued | 9/14/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/25/2022 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Hall,, Ralph Michael; Lic. No.: C87047 | 1854 MELROSE ST KLAMATH FALLS, OR 97601 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/21/2023 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 10/17/2023 | Corrections Issued | JOHNNY MIRANDA |
| Excavation | 10/17/2023 | Corrections Issued | JOHNNY MIRANDA |
| Initial Grading | 10/17/2023 | Corrections Issued | JOHNNY MIRANDA |
| Excavation | 10/23/2023 | Partial Approval | JOHNNY MIRANDA |
| Initial Grading | 10/30/2023 | Partial Approval | JOHNNY MIRANDA |
| Excavation | 12/5/2023 | Partial Inspection | MATTHEW JENKINS |
| Special/Order Compliance | 12/5/2023 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 1/29/2024 | Corrections Issued | JOHNNY MIRANDA |
| Sub-Drain | 1/31/2024 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 9/5/2024 | Approved | VASIL MIHALEV |
| Drainage Devices/Catch Basin | 9/18/2024 | Approved | VASIL MIHALEV |